Question 1 of 5
An organization is implementing a digital transformation initiative to replace legacy systems with cloud-based platforms. Eighteen months into a planned 24-month program, only 30% of the technical migration is complete and user adoption is at 15%. What is the MOST likely root cause and appropriate response?
- A.The transformation underweighted change management — the technical migration was prioritized over people adoption.
- B.The technology was poorly chosen — replace the cloud platform with an on-premises solution
- C.The project team lacks technical skills — hire more developers to accelerate migration
- D.The timeline was too aggressive — extend the program to 36 months and proceed with the same approach
Show answer and explanation
Correct answer: A
Research consistently shows that digital transformations fail not because of technology, but because of inadequate change management and adoption planning. A 15% adoption rate at 75% of schedule elapsed is a clear signal that the human side was neglected. Replacing the platform starts over without addressing the real problem. Adding developers solves technical output speed but not organizational readiness. Extending the timeline without changing the approach will produce the same outcome on a longer schedule.