Question 1 of 16
A project was completed on time and on budget, but six months after go-live the business unit reports the expected productivity gains have not materialized. Who is responsible for benefits realization?
- A.The project manager, who should have built benefits measurement milestones into the schedule and tracked realization as part of formal project delivery.
- B.The project sponsor and business owner, who are accountable for realizing the strategic benefits post-delivery.
- C.The project team, who built the solution
- D.The PMO, which should have tracked benefits after project closure
Show answer and explanation
Correct answer: B
Benefits realization is the responsibility of the project sponsor and business owner. The project manager delivers outputs; the business translates outputs into outcomes and benefits. Post-project benefits are tracked by operational owners, not the project team or PMO by default. The PM's role ends at delivery, though they may support the transition plan.