Question 1 of 15
Midway through a project, the organization announces a strategic pivot that makes two of the project's four deliverables irrelevant to the new business direction. What should you do FIRST?
- A.Reassess the project's business case and present options to the sponsor: realign scope, pause, or close the project.
- B.Continue delivering all four deliverables as originally planned to avoid scope changes
- C.Stop all project work now until new strategic direction is clarified
- D.Deliver the two relevant deliverables early and close the project
Show answer and explanation
Correct answer: A
When strategic direction changes, a project manager must reassess the business case. Projects that no longer align with organizational strategy may need to be realigned, paused, or terminated — not blindly continued. Continuing unchanged wastes resources. Stopping immediately is premature without analysis. Delivering early without sponsor approval bypasses governance.