Question 1 of 10
Environmental scanning shows that new legislation may open an adjacent market much larger than the original target. What should the project manager do FIRST?
- A.Ignore the environmental scanning finding because external factors are formally outside the defined project boundary and scope.
- B.Change scope now without sponsor input or formal approval so the opportunity is not lost in the change control queue.
- C.Document and assess the strategic impact so leadership can decide whether the project should adapt, continue, or change scope.
- D.Wait until the next annual planning cycle or scheduled portfolio review to formally raise the environmental scan finding.
Show answer and explanation
Correct answer: C
External environment changes can materially alter risk and value. The project manager should surface the finding, assess impact, and support a governance decision. Ignoring the environment or changing scope unilaterally are both poor responses.