Question 1 of 21
Your organization's PMO requires monthly status reports, but your agile project already produces sprint reviews with the same information. The reporting overhead is consuming three hours of your team's time each month. What is the BEST course of action?
- A.Skip the PMO status reports entirely and rely only on sprint review artifacts, without raising the conflict or seeking a formal agreement with the PMO on acceptable reporting formats.
- B.Comply with both reporting mechanisms in full without raising the duplication issue, accepting the overhead as a necessary cost of operating in an organization with formal PMO governance.
- C.Have the team build automation to generate PMO reports from sprint data to save time, without engaging the PMO to determine whether existing agile artifacts already satisfy their needs.
- D.Work with the PMO to determine if sprint review artifacts can satisfy the reporting requirement, reducing duplicate effort.
Show answer and explanation
Correct answer: D
The right approach is to collaborate with the PMO to align processes. Sprint artifacts often contain everything a status report needs — the goal is to eliminate redundancy through dialogue, not unilateral action. Skipping PMO reports violates governance. Silent compliance perpetuates inefficiency. Automation reduces time but doesn't solve the duplication problem.