Question 1 of 10
An organization finds that projects use inconsistent methods and executives cannot compare status across the portfolio. What is the MOST appropriate response?
- A.Increase reporting volume for every project without changing decision criteria or the governance structures that translate data into better portfolio decisions.
- B.Allow each project to define success independently, eliminating portfolio-level visibility in favor of team autonomy and locally defined delivery criteria.
- C.Use the PMO and portfolio governance structure to standardize visibility, prioritization, and decision making in proportion to organizational need.
- D.Focus only on the largest project because portfolio governance adds little value to smaller and mid-priority initiatives in the portfolio.
Show answer and explanation
Correct answer: C
A PMO should help the organization make better project and portfolio decisions, not just collect templates. The best response is to introduce the right level of standardization, transparency, and prioritization so leaders can compare initiatives and allocate resources intentionally.