Portfolio, Program, Operations, and Closure PMP Practice Questions

Test yourself with 25 free, scenario-based PMP practice questions on portfolio, program, operations, and closure, drawn from the Business Environment domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Question 1 of 25

A portfolio manager informs you that two projects in the portfolio — yours and another — are competing for the same senior technical resources and are targeting identical customer segments. Your project has a higher NPV but the other project was started six months earlier. What is the BEST course of action?

  1. A.Escalate to the portfolio manager to conduct a formal prioritization review, presenting both projects' strategic value metrics for comparison.
  2. B.Negotiate directly with the other project manager to informally share the contested resources without escalating the conflict to portfolio or senior leadership.
  3. C.Accelerate your project timeline to finish before the conflict becomes critical
  4. D.Reduce your project scope to eliminate the resource conflict
Show answer and explanation

Correct answer: A

Portfolio-level resource conflicts require portfolio-level governance decisions. The portfolio manager is responsible for balancing competing projects based on strategic value, not start dates. Peer negotiation bypasses governance and may sub-optimize the portfolio. Accelerating or reducing scope are unilateral decisions that ignore the organization's need to maximize portfolio value.

Question 2 of 25

You are a project manager within a program that is rolling out a new ERP system across five business units. Two of your deliverables feed directly into another project in the program. The other project manager reports your latest delay will push their go-live date by three weeks. What is the MOST appropriate action?

  1. A.Work overtime to eliminate your delay without notifying the program manager
  2. B.Inform the program manager now so the interdependency impact can be assessed at the program level and recovery options planned.
  3. C.Tell the other project manager to rebuild their schedule to absorb the delay without escalating the interdependency to the program manager.
  4. D.Submit a change request to extend both projects' timelines
Show answer and explanation

Correct answer: B

In a program environment, interdependency impacts must be escalated to the program manager, who has visibility across all projects and can coordinate recovery. Hiding the delay denies the program manager the information needed to protect overall program outcomes. Telling the other PM to absorb it ignores your accountability. Submitting change requests is premature without first assessing options with the program manager.

Question 3 of 25

Your agile team is working on a product that is one component of a larger strategic program. The program office asks your team to freeze the current release to align with a program-wide go-live date that is six weeks away, even though your team has two high-priority backlog items that could deliver significant user value. What should you do?

  1. A.Ignore the program freeze and deliver the backlog items on your original schedule — your team's sprint commitment takes priority, and the program office can adjust the go-live alignment accordingly.
  2. B.Accept the freeze immediately without raising the trade-off — program governance decisions are not negotiable, and advocating for exceptions risks damaging your team's standing with the program office.
  3. C.Present the value at stake from the two backlog items to the program manager and jointly decide whether an exception is warranted or the items should be deferred to the next release cycle.
  4. D.Add the backlog items to the next sprint without informing the program office, since team-level backlog decisions are within the product owner's authority and do not require program-level approval.
Show answer and explanation

Correct answer: C

Agile projects within programs must balance team autonomy with program-level coordination. Raising the value trade-off transparently enables an informed decision at the right level. Ignoring the freeze undermines program integrity. Silent compliance sacrifices value without discussion. Covert additions violate the spirit of the freeze agreement.

Question 4 of 25

A portfolio review reveals that three of the eight active projects in your organization are underperforming against strategic objectives. As a senior project manager advising the portfolio committee, which TWO actions are MOST aligned with portfolio management best practices?

Select all that apply.

  1. A.Continue all projects to avoid disrupting team morale and stakeholder relationships
  2. B.Realign underperforming projects by updating their business cases and adjusting objectives to match current strategy.
  3. C.Transfer resources from underperforming projects to higher-priority initiatives
  4. D.Increase project budgets to give underperforming projects a better chance of success
  5. E.Terminate projects that cannot demonstrate a credible path to strategic value, regardless of sunk costs
Show answer and explanation

Correct answers: B and E

Portfolio management requires ruthless focus on strategic value. Terminating projects that cannot justify continuation prevents sunk cost fallacy from draining resources. Realigning business cases gives salvageable projects a structured path to relevance. Continuing everything dilutes portfolio value. Transferring resources may be a consequence but not the first action. Increasing budgets for underperformers without strategic justification is wasteful.

Question 5 of 25

A project to build a new retail distribution center is 60% complete when the organization announces it is exiting the retail market entirely due to a strategic acquisition. The project sponsor asks the project manager to shut down the project. The sunk cost is $8.2M. What is the MOST important consideration in the closure decision?

  1. A.Whether completing the project would add any value given the new strategic direction — the $8.2M already spent is irrelevant to the forward-looking decision.
  2. B.Recovering as much of the $8.2M sunk cost as possible through asset sales
  3. C.Protecting the project team's employment by finding ways to continue the project
  4. D.Completing the project to 100% to preserve organizational credibility with contractors, treating the reputational cost of stopping as more important than the strategic cost of continuing.
Show answer and explanation

Correct answer: A

The sunk cost fallacy is one of the most dangerous biases in project governance. Past investment ($8.2M) is irrelevant to the decision to continue or terminate — what matters is whether completing the project delivers future value given the new strategic context. Since the organization is exiting retail entirely, completing the distribution center would be irrational. Asset recovery is a valid closure activity but not the primary decision factor. Team employment is a human resources concern separate from the termination decision. Completing for credibility substitutes social discomfort for sound analysis.

Question 6 of 25

A project is terminated early due to budget cuts. The project has produced three of five planned deliverables. What should the project manager do to properly close the project?

  1. A.Stop all work immediately and notify stakeholders that the project is terminated — since the decision was made at the executive level, formal project closure processes are already covered by the termination order.
  2. B.Conduct a formal closure process: document completed work, hand off usable deliverables to operations, release resources formally, capture lessons learned, update organizational records.
  3. C.Archive the project plan as the primary project record and issue a formal closure notice — the plan documents the full intended scope, and stakeholders have already been informed through the executive decision.
  4. D.Place the project on administrative hold rather than formally closing it — this preserves all contracts, resources, and momentum so work can restart quickly if additional funding becomes available.
Show answer and explanation

Correct answer: B

Even when a project is terminated early, PMBOK requires a formal closure process. This includes documenting what was completed, ensuring usable deliverables are transitioned to operations or the business (the three completed outputs have value), releasing team members formally, closing vendor contracts, capturing lessons learned, and updating organizational records. Simply stopping leaves financial, contractual, and knowledge management loose ends. Archiving only the project plan is insufficient. Indefinite hold consumes budget allocation and leaves resources in limbo.

Question 7 of 25

A program manager is overseeing four related projects aimed at launching a new product line. One project — the market research initiative — is chronically behind schedule and its findings are needed as inputs by all three other projects. What should the program manager do?

  1. A.Let each project manager solve the problem independently
  2. B.Terminate the market research project and have the other projects proceed without the research
  3. C.Assess the program-level impact of the market research delay, determine whether interim findings can unblock the other projects.
  4. D.Request additional resources for the market research project without first assessing downstream impacts on the other three interdependent projects.
Show answer and explanation

Correct answer: C

Program management adds value precisely by managing interdependencies between projects. The program manager should take a holistic view: can interim findings provide enough input to unblock downstream projects? Does the program schedule need to be restructured? Can parallel tracks be activated? Leaving each PM to solve it independently ignores the program-level visibility and authority that exists to address exactly this. Terminating market research removes the program's knowledge foundation. Adding resources without impact assessment may accelerate the wrong work.

Question 8 of 25

An organization has a portfolio of 12 active projects. A portfolio review reveals that four projects are strategically low-priority, three are medium-priority, and five are high-priority. Resources are constrained and can only fully support eight projects simultaneously. What portfolio management action should be taken?

  1. A.Reduce all 12 project budgets proportionally to distribute resources equally, regardless of each project's strategic value, urgency, or benefit-to-cost ratio.
  2. B.Continue all 12 projects at reduced capacity to keep all commitments
  3. C.Prioritize the five high-priority projects for full resourcing, allocate remaining capacity to medium-priority projects based on strategic value.
  4. D.Select 8 projects randomly to avoid stakeholder conflict
Show answer and explanation

Correct answer: C

Portfolio management exists to optimize resource allocation toward highest strategic value. When capacity is constrained, the disciplined response is to concentrate resources on high-value projects rather than diluting effort across all projects, which tends to make all projects slower and less successful. Equal budget reduction uniformly degrades all projects. Continuing all 12 at reduced capacity is the worst outcome — all projects are under-resourced and likely to underperform. Random selection ignores strategic alignment entirely.

Question 9 of 25

A PMO director is presenting the quarterly portfolio dashboard to the executive committee. Three projects are green (on track), two are yellow (minor concerns), and one is red (critical issues). The executive committee focuses only on the red project and asks the PMO director to resolve it. What ADDITIONAL information should the PMO director provide to enable effective portfolio decision-making?

  1. A.The detailed technical architecture of the red project — the executive committee needs to understand the root cause complexity to make an informed decision about recovery options, additional investment, or termination.
  2. B.The project manager's performance history and track record — establishing accountability is essential before committing additional executive attention or budget to recovering a project in critical status.
  3. C.A comparison of the red project's timeline against industry benchmarks for similar project types — this contextualizes whether the delays reflect execution failures or are consistent with comparable initiatives.
  4. D.Whether the red project's issues will affect any of the other portfolio projects through shared resources, dependencies, or strategic conflicts, and what portfolio-level options exist — recover, reallocate, or terminate.
Show answer and explanation

Correct answer: D

Effective portfolio governance requires more than project-level issue management — it requires cross-portfolio impact analysis. The red project's critical issues may be depleting resources or blocking deliverables needed by the green and yellow projects. The committee needs portfolio-level options, not just project-level fixes. Technical architecture is execution detail inappropriate for executive review. Performance history addresses accountability but not the portfolio impact. Industry benchmarks provide context but not actionable portfolio insight.

Question 10 of 25

An agile product team has been building a consumer application for 14 months. During a quarterly business review, the executive team determines the market opportunity has diminished significantly — a major platform player entered the space and now owns 60% of the target market. The product owner recommends continuing to find a niche. The CFO recommends immediate termination. As the project manager, what framework should guide this decision?

  1. A.The team's sprint velocity and remaining backlog size — if the team can deliver the remaining features within two or three more sprints, the sunk cost justifies completing the product before reassessing market fit.
  2. B.The original project charter approved 14 months ago — the charter established the strategic rationale and success criteria, and any decision to continue or terminate must be measured against the original business intent.
  3. C.The product owner's domain expertise and market judgment — they have been closest to customer feedback throughout the 14 months and are best positioned to assess whether a viable niche strategy can succeed.
  4. D.A revised business case assessment that tests whether a viable niche market exists with sufficient NPV to justify continued investment, compared against the opportunity cost of deploying the team elsewhere.
Show answer and explanation

Correct answer: D

Continuation vs. termination decisions must be grounded in a current assessment of expected future value versus the cost of continuation and the opportunity cost of not deploying resources elsewhere. The niche market hypothesis needs validation: Is there an addressable market? What revenue/value does it represent? How does its NPV compare to alternative uses of the same team? Sprint velocity measures delivery efficiency, not strategic viability. The original charter was written in a different market context and is obsolete. The product owner's judgment is valuable input but not a sufficient decision framework for an investment continuation decision.

Question 11 of 25

An agile team has delivered the final increment of a customer self-service portal, and the sponsor wants to move the team to a new product next week. The customer support operations manager has not accepted ownership of the portal, saying the support staff have no runbooks and have never handled its types of incidents. What should the project manager do FIRST?

  1. A.Close the project as planned and pass the remaining portal backlog to the support operations manager to prioritize.
  2. B.Meet the support operations manager to assess what the support staff need before they can accept the portal.
  3. C.Keep the full team on portal support in production until the support operations manager says the staff are ready.
  4. D.Ask the sponsor to direct the support operations manager to sign the portal acceptance before the team moves on.
Show answer and explanation

Correct answer: B

Operations has a concrete reason for refusing ownership, so the project manager should first understand exactly what the support staff need, such as runbooks and incident training, and build that into a defined handover. Closing the project and passing the backlog to support transfers a product that the receiving team cannot yet run. Keeping the whole team on production support with no defined end turns the project into ongoing operations. Having the sponsor force a sign-off may get a signature, but it leaves the readiness gap in place and damages the relationship with the people who will own the portal.

Question 12 of 25

Midway through a predictive project to build compliance reporting software, the regulation the software was built for is repealed. The project manager has updated the business case, and the revised analysis shows the remaining benefits are now well below the remaining cost, although 60 percent of the budget is already spent. What should the project manager do NEXT?

  1. A.Continue executing the approved plan with 60 percent of the budget already spent, and report the value gap at closing.
  2. B.Submit a change request that cuts the remaining scope to the reports still useful and lowers the remaining budget.
  3. C.Pause the team's work and start the closure activities, then brief the sponsor on the revised business case.
  4. D.Present the updated business case to the sponsor with a recommendation to terminate the project early.
Show answer and explanation

Correct answer: D

The analysis is already done and shows the project no longer justifies further investment, and a decision to terminate belongs to the sponsor and governance, not the project manager. Presenting the updated business case with a clear recommendation gives the decision makers what they need. Continuing to protect the money already spent is a sunk-cost argument that wastes the remaining budget. A scope-reduction change request assumes the project should continue, which is the very question the sponsor must answer. Pausing the work and starting closure before briefing the sponsor gets the order wrong, because the project manager would be acting on a termination decision that only the sponsor can make.

Question 13 of 25

Leaders at a retail company are debating how to manage the move of its 40 branch offices to a new network. IT operations calls the work routine maintenance, while the strategy office wants a program. The migration must finish by a fixed date, each branch cutover is a distinct effort with its own local team and schedule, and the shared benefit is a lower network cost. What is the BEST recommendation for the project manager to make?

  1. A.Recommend managing the cutovers as a program of related projects, with the finished network handed to IT operations.
  2. B.Recommend that IT operations absorb the 40 cutovers into its routine maintenance schedule and its operating budget.
  3. C.Recommend one large project covering the 40 branches, with the strategy office acting as its sponsor and reviewer.
  4. D.Set up 40 separate projects, each owned by its branch manager and reporting its weekly cutover progress to IT operations.
Show answer and explanation

Correct answer: A

The migration is temporary and has a fixed end, so it is not routine operations, and it consists of many distinct cutovers whose combined result produces a shared benefit. That fits a program of related projects, with the steady-state network handed to IT operations when the work ends. Absorbing the cutovers into maintenance hides a time-bound change effort inside the operating budget without coordinated governance. A single large project would treat 40 separate efforts with their own teams and schedules as one, losing the benefit-level coordination a program provides. Running 40 branch-owned projects that only report progress to IT operations tracks status but leaves no one managing the dependencies between cutovers or the combined cost benefit.

Question 14 of 25

Three agile teams are building separate parts of a new loyalty offering: a mobile app, a point-of-sale integration, and a partner portal. Each team has its own product owner, and the loyalty benefits appear only when the three parts work together. The product owners meet weekly but cannot settle trade-offs, because each is measured on their own product's metrics. What is the BEST action for the project manager?

  1. A.Move the product owner meeting from weekly to daily and add a shared dependency board for the three teams.
  2. B.Merge the three teams into one large team with a single backlog managed by the most senior product owner.
  3. C.Ask the sponsor to group the three efforts into a program with one owner accountable for the loyalty benefits.
  4. D.Have each team add stories for its dependencies on the other two teams to its own backlog and track them there.
Show answer and explanation

Correct answer: C

The product owners already meet, and the real problem is that no one is accountable for the shared outcome, so each optimizes for their own metrics. Managing the three related efforts as a program with an owner of the loyalty benefits creates the coordinated governance the outcome needs, and setting that structure up is a decision for the sponsor. Meeting daily adds time together but leaves the conflicting incentives in place. Merging everything into one oversized team undermines the small-team model and still lacks benefit-level ownership. Tracking dependency stories in each backlog makes dependencies visible but does not resolve the trade-offs.

Question 15 of 25

A portfolio review board compared a predictive warehouse automation project with three new proposals and decided to terminate the project, whose value now trails the newer opportunities. The team is halfway through building the second of four conveyor zones. What should the project manager do NEXT?

  1. A.Complete the second conveyor zone with the current team, then start the closure activities for the project.
  2. B.Start the closure process: record the state of each conveyor zone, capture lessons learned, release the team.
  3. C.Ask the board to reconsider the decision, showing how little schedule remains and the impact on team morale.
  4. D.Release the team to the three new proposals this week and complete the project records when time allows.
Show answer and explanation

Correct answer: B

The termination decision has been made by the body that has the authority to make it, so the project manager should carry out closure for a terminated project. That means documenting where each deliverable stands, capturing lessons learned, and releasing resources in an orderly way. Finishing the second zone first spends more money on work the board has decided to stop. Asking the board to reverse its decision on schedule and morale grounds ignores the value comparison that drove it. Releasing the team before the records are complete risks losing knowledge about the partial deliverables that the organization may need later.

Question 16 of 25

A hybrid project is launching a premium travel booking app, with the platform built in predictive phases and features delivered in sprints. A competitor has just released a free app with similar features, and the sponsor asks the project manager whether the project should be closed early. What should the project manager do FIRST?

  1. A.Reassess the business case using the new market data to see if remaining benefits still justify remaining cost.
  2. B.Advise the sponsor to continue the project to its approved baseline, with the platform phases nearly complete.
  3. C.Recommend that the sponsor close the project now and redirect the remaining budget to a response to the competitor.
  4. D.Use the next sprint retrospective to have the team evaluate how the competitor's app affects their remaining features.
Show answer and explanation

Correct answer: A

The sponsor needs a value-based answer, and the market shift may or may not have removed the project's benefits, so the project manager should first update the business case with the new data and compare remaining benefits to remaining cost. Recommending continuation because the baseline is approved and work is nearly done ignores the changed market. Recommending immediate closure assumes the outcome of an analysis that has not been done. A sprint retrospective is for improving how the team works, and the team alone is not the right forum to judge the project's business viability.

Question 17 of 25

The customer analytics team at an insurer asks the PMO to set up its work as an agile project so it can access project funding. The work is a monthly refresh of claims dashboards with no end date, plus a one-time move of those dashboards to a new data platform. What is the BEST response from the PMO lead?

  1. A.Set up a long-running agile project for the analytics work, with quarterly backlog reviews.
  2. B.Ask the portfolio board to rule on whether recurring dashboard refresh work may receive agile project funding.
  3. C.Decline the request and tell the analytics team to absorb the refresh and the platform move into current work.
  4. D.Classify the monthly refresh as operations work and set up only the platform move as an agile project.
Show answer and explanation

Correct answer: D

The monthly refresh is ongoing and repetitive, which makes it operations, while the platform move is temporary and produces a unique result, which makes it a project. Classifying work against these standard definitions is within the PMO lead's role, and it routes each part to the right funding channel. A long-running project for recurring work blurs the line between projects and operations and keeps project governance on work that never ends. Sending the question to the portfolio board escalates a classification the PMO lead can make; the board is needed only if the funding itself is disputed. Declining everything ignores that the platform move is legitimate project work that may need dedicated funding.

Question 18 of 25

A portfolio committee must choose between continuing a predictive ERP upgrade that has already spent $2 million and is now forecast to deliver little value, and funding a new supplier portal with a stronger business case. Only one can be funded this year. The portfolio manager is preparing the decision package. What is MOST important for the package to contain?

  1. A.A comparison of both on total lifetime cost, including the $2 million already spent on the ERP upgrade, against value.
  2. B.A recommendation to finish the ERP upgrade first and fund the supplier portal in the next annual budget cycle.
  3. C.A comparison of both on remaining cost, expected value, and strategic fit, leaving out the $2 million already spent.
  4. D.A summary of each sponsor's case, presented by the sponsors, for the committee to vote on at its next meeting.
Show answer and explanation

Correct answer: C

Portfolio decisions should look forward: what each option will still cost, what value it will deliver, and how well it fits strategy. Money already spent on the ERP upgrade cannot be recovered and should not influence the choice. Including the $2 million in a lifetime cost comparison builds the sunk cost into the decision. Recommending that the ERP upgrade be finished first prejudges the outcome against the stronger business case. A vote on the sponsors' presentations rewards persuasion rather than an objective comparison of value.

Question 19 of 25

A hybrid project is about to deploy a new warehouse management system. The business case promises 20 percent faster order picking, but that benefit will appear only over the 12 months after go-live, as warehouse staff adopt the new process, and the project closes one month after go-live. What is the MOST important step before the project closes?

  1. A.Extend the project for twelve months after go-live and have the project team measure the picking times directly.
  2. B.Agree with the warehouse operations manager on who will measure picking times after go-live and report the results.
  3. C.Add the 20 percent target to the acceptance criteria and close the project once the system passes acceptance testing.
  4. D.Hand the benefits register to the PMO at closure and let the PMO decide who should track the picking improvement.
Show answer and explanation

Correct answer: B

The benefit depends on sustained operational use, so ownership of measuring and reporting it must sit with operations, and it must be agreed before the project team disbands. Making that agreement with the warehouse operations manager connects project delivery to benefits realization. Extending the project for a year keeps a temporary team in place for work that belongs to operations. Adding the target to acceptance criteria cannot work, because the benefit cannot appear during testing. Handing the register to the PMO without a named owner in operations leaves the benefit without anyone accountable for it.

Question 20 of 25

An agile product team launched a budgeting app six months ago, and adoption is far below the target in the business case. The product owner keeps adding features, the sponsor keeps approving another quarter of funding, and nobody can say what result would justify stopping. How should the project manager address this?

  1. A.Help the sponsor and product owner agree on the adoption thresholds that will trigger a pivot or stop decision.
  2. B.Keep funding the team through the end of the fiscal year, then judge the app on its full year of adoption results.
  3. C.Stop the initiative now and move the team to the next product on the roadmap at the start of the next sprint.
  4. D.Run a retrospective with the team to evaluate why adoption is low and agree on the next features to try.
Show answer and explanation

Correct answer: A

The core problem is that there are no agreed criteria for continuing or stopping, so each funding decision is made by default. Helping the sponsor and product owner set adoption thresholds tied to a pivot or stop decision gives future reviews an objective basis. Funding through year end postpones the decision without criteria and may waste more money. Stopping now is not the project manager's call and may be premature without defined thresholds. A team retrospective about new features continues the same pattern of adding features without deciding what success looks like.

Question 21 of 25

A project team is delivering efficiently, but product decisions are not grounded in clear user or market outcomes. Which practice is MOST needed?

  1. A.More detailed sprint-level reporting and status documentation, giving leadership better visibility into team activity and task-level progress.
  2. B.Stronger product management discipline linking backlog decisions to user needs, market evidence, and value hypotheses.
  3. C.A larger change control board with more stakeholder representatives, so that backlog decisions have broader organizational input before delivery begins.
  4. D.A stricter time reporting policy for the delivery team, so project managers can track labor hours and identify capacity issues more accurately.
Show answer and explanation

Correct answer: B

PMBOK 8 explicitly recognizes product management considerations. Efficient delivery is not enough if what is being delivered is not tied to real value hypotheses.

Question 22 of 25

A product owner wants to prioritize a feature because a senior executive asked for it informally, but market data suggests low customer value. What should the project manager encourage?

  1. A.Immediate prioritization because executive interest is the clearest signal of organizational value, and product owners should treat executive sponsorship as the primary backlog input.
  2. B.Deferral of all product decisions to the PMO
  3. C.A value-based discussion using product evidence, strategy, and stakeholder input rather than seniority alone
  4. D.Treat the request as mandatory scope
Show answer and explanation

Correct answer: C

Product management decisions should be evidence-informed. Seniority can matter, but PMBOK 8’s value orientation points toward testing value rather than assuming it.

Question 23 of 25

A department asks for project funding to support an activity that has no clear end date and consists mainly of recurring service delivery. How should this be classified?

  1. A.More likely as operations work unless there is a distinct temporary change initiative with a defined end and outcome.
  2. B.As a project, because all important organizational work should be treated as a project with a PM, regardless of whether it has a defined end date or unique deliverable.
  3. C.As a program automatically
  4. D.As a risk management activity
Show answer and explanation

Correct answer: A

PMBOK distinguishes temporary change efforts from ongoing operational work. The classification should reflect whether the effort is temporary and outcome-focused.

Question 24 of 25

A portfolio board must choose between continuing a low-value legacy project and funding a new higher-value opportunity. Which decision principle is BEST?

  1. A.Protect the legacy project because stopping work signals failure
  2. B.Compare future value, strategic fit, and opportunity cost rather than defending sunk cost
  3. C.Split the budget evenly to avoid conflict
  4. D.Let whichever sponsor has more influence decide
Show answer and explanation

Correct answer: B

Portfolio decisions should be forward-looking and value-based. Opportunity cost and strategic fit matter more than sunk cost or politics.

Question 25 of 25

Several related projects must be coordinated because the benefits only emerge when their outputs work together. What organizational construct is MOST appropriate?

  1. A.Operations management
  2. B.A program, because coordinated management is needed to realize combined benefits
  3. C.A single oversized project no matter how different the work is
  4. D.A procurement office
Show answer and explanation

Correct answer: B

Programs coordinate related work to realize benefits that individual projects cannot fully deliver alone.