PMPRocket
PMP Practice QuestionsEarned Value Management
Process Domain

Earned Value Management PMP Practice Questions

Test yourself with 22 free, scenario-based PMP practice questions on earned value management, drawn from the Process domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Study first: earned value management explained · PMP formulas cheat sheet

Question 1 of 22

Your project has a BAC of $500,000. At the status date, the EV is $200,000 and the AC is $250,000. What does this tell you about project performance?

  1. A.The project is over budget for the work completed
  2. B.The project is under budget and ahead of schedule
  3. C.The project has spent more than the planned budget allocation
  4. D.The project is on schedule but has scope issues
Show answer and explanation

Correct answer: A

Cost Performance Index (CPI) = EV / AC = 200,000 / 250,000 = 0.8. A CPI < 1 means you are spending more than the value earned — the project is over budget. We cannot determine schedule performance without PV. The project has not necessarily overspent its total budget — it is over budget for work completed to date.

Question 2 of 22

A construction project has a BAC of $800,000. After six months, the PV is $320,000, the EV is $280,000, and the AC is $300,000. What is the Schedule Performance Index (SPI) and what does it indicate?

  1. A.SPI = 0.875 — the project is progressing at 87.5% of the planned rate and is behind schedule
  2. B.SPI = 1.07 — the project is slightly ahead of schedule
  3. C.SPI = 0.93 — the project is progressing at 93% of the planned rate and is behind schedule
  4. D.SPI = 1.14 — the project is ahead of schedule
Show answer and explanation

Correct answer: A

SPI = EV / PV = $280,000 / $320,000 = 0.875. An SPI less than 1.0 indicates the project is behind schedule, completing only 87.5 cents of planned work for every $1 of work planned. Note: the CPI = EV / AC = $280,000 / $300,000 = 0.933, meaning the project is also slightly over budget. SPI of 0.93 would require EV/PV = 0.93, which is not the case here.

Question 3 of 22

Your project has a BAC of $1,200,000. The current CPI is 0.75 and the EV to date is $450,000. Using the EAC formula based on current CPI performance, what is the Estimate at Completion (EAC)?

  1. A.$1,350,000
  2. B.$1,600,000
  3. C.$1,500,000
  4. D.$900,000
Show answer and explanation

Correct answer: B

When future performance is expected to match current CPI, EAC = BAC / CPI = $1,200,000 / 0.75 = $1,600,000. This formula assumes the cost variance trend will continue throughout the project. AC = EV / CPI = $450,000 / 0.75 = $600,000. ETC = EAC - AC = $1,600,000 - $600,000 = $1,000,000 remains to be spent. The other options result from incorrect formula application.

Question 4 of 22

A software project has: BAC = $500,000, AC = $180,000, EV = $150,000, PV = $200,000. The sponsor asks how much MORE money is needed to complete the project, assuming future work performs at the planned rate. What is the Estimate to Complete (ETC)?

  1. A.$320,000
  2. B.$366,667
  3. C.$350,000
  4. D.$300,000
Show answer and explanation

Correct answer: C

When future work is assumed to perform at the original planned rate (CPI = 1.0 going forward), ETC = BAC - EV = $500,000 - $150,000 = $350,000. This formula (ETC = BAC - EV) is used when the variances to date are considered atypical and future performance will revert to the plan. If you assumed current CPI (0.833) would continue: ETC = (BAC - EV) / CPI = $350,000 / ($150,000 / $180,000) = $420,000, giving EAC = $600,000, but that is not the assumption the sponsor asked for.

Question 5 of 22

Your project must be completed within its $600,000 BAC. Currently: EV = $240,000, AC = $270,000. What is the To-Complete Performance Index (TCPI) needed to finish within the original BAC?

  1. A.TCPI = 0.91 — the required efficiency for remaining work is below current performance, suggesting the project has more budget flexibility than the CPI alone would indicate.
  2. B.TCPI = 1.0 — maintaining current efficiency is sufficient to complete the project within the BAC, indicating no change in cost management approach is required.
  3. C.TCPI = 0.85 — the project can relax cost efficiency for remaining work, indicating the current spending rate leaves more budget headroom than needed to meet the BAC.
  4. D.TCPI = 1.09 — the remaining work must be done more efficiently than the current CPI of 0.89 to meet the BAC
Show answer and explanation

Correct answer: D

TCPI (based on BAC) = (BAC - EV) / (BAC - AC) = ($600,000 - $240,000) / ($600,000 - $270,000) = $360,000 / $330,000 = 1.09. A TCPI above 1.0 means the remaining work must be done more efficiently than planned, and here it is well above the current CPI (EV / AC = $240,000 / $270,000 = 0.89). Since the required efficiency is higher than what the team has achieved so far, finishing within the BAC will be difficult. A TCPI below 1.0 or exactly 1.0 would only apply if the project were on or under budget, which it is not.

Question 6 of 22

A project with BAC = $400,000 is at month 4 of a planned 10-month schedule. PV = $160,000, EV = $120,000, AC = $140,000. What are the Cost Variance (CV) and Schedule Variance (SV)?

  1. A.CV = -$20,000 (over budget); SV = -$40,000 (behind schedule)
  2. B.CV = +$20,000 (under budget); SV = -$40,000 (behind schedule)
  3. C.CV = -$20,000 (over budget); SV = +$40,000 (ahead of schedule)
  4. D.CV = -$40,000 (over budget); SV = -$20,000 (behind schedule)
Show answer and explanation

Correct answer: A

CV = EV - AC = $120,000 - $140,000 = -$20,000. A negative CV means the project is over budget (spent more than the value earned). SV = EV - PV = $120,000 - $160,000 = -$40,000. A negative SV means the project is behind schedule (completed less work than planned). Both variances are negative, indicating the project is both over budget and behind schedule.

Question 7 of 22

A project manager is reviewing performance data: BAC = $250,000, EV = $175,000, AC = $160,000, PV = $200,000. The project end date is fixed. Which statement BEST describes the project's current status?

  1. A.The project is over budget and ahead of schedule
  2. B.The project is under budget and behind schedule
  3. C.The project is under budget and ahead of schedule
  4. D.The project is over budget and behind schedule
Show answer and explanation

Correct answer: B

CPI = EV / AC = $175,000 / $160,000 = 1.094. CPI > 1 means the project is under budget (earning more value per dollar spent). SPI = EV / PV = $175,000 / $200,000 = 0.875. SPI < 1 means the project is behind schedule (completing less work than planned). Therefore the project is under budget but behind schedule. The CV = EV - AC = +$15,000 (favorable) and SV = EV - PV = -$25,000 (unfavorable) confirm this analysis.

Question 8 of 22

At project completion, the final AC is $920,000 and the BAC was $800,000. What is the final Cost Variance (CV) and what does it mean?

  1. A.CV = +$120,000; the project came in under budget
  2. B.CV = $0; the project met its budget since EV equals BAC at completion
  3. C.CV = -$120,000; the project exceeded its budget by $120,000
  4. D.CV cannot be calculated without knowing the EV
Show answer and explanation

Correct answer: C

At project completion, all planned work is complete, so EV = BAC = $800,000. CV = EV - AC = $800,000 - $920,000 = -$120,000. A negative final CV means the project spent $120,000 more than budgeted. CPI at completion = $800,000 / $920,000 = 0.87. CV can be calculated without a reported EV because at completion EV always equals BAC by definition: all work has been accomplished.

Question 9 of 22

You are 60% through your project. BAC = $300,000, AC = $210,000, EV = $180,000. The project sponsor demands the project must finish within the original BAC. Calculate the TCPI to finish within BAC and assess feasibility.

  1. A.TCPI = 0.90; the project can afford to reduce efficiency slightly
  2. B.TCPI = 1.0; the project is exactly on track to meet the BAC
  3. C.TCPI = 1.20; challenging but achievable with process improvements
  4. D.TCPI = 1.33; highly unlikely to achieve since it requires 33% more efficiency than planned
Show answer and explanation

Correct answer: D

TCPI (to BAC) = (BAC - EV) / (BAC - AC) = ($300,000 - $180,000) / ($300,000 - $210,000) = $120,000 / $90,000 = 1.333. This means the remaining work must be done 33% more efficiently than planned — at a much higher rate than the current CPI = EV / AC = $180,000 / $210,000 = 0.857. A TCPI significantly above 1.0, especially when far above the current CPI, makes the BAC target practically unrealistic and warrants a revised EAC.

Question 10 of 22

A project manager calculates EAC = AC + (BAC - EV). When is this formula MOST appropriate to use?

  1. A.When current variances are considered atypical and future work is expected to proceed at the originally planned rate.
  2. B.When current cost variances are expected to continue at the same rate through project completion
  3. C.When the original estimate is considered fundamentally flawed and must be re-estimated from scratch
  4. D.When both CPI and SPI must be factored into the estimate
Show answer and explanation

Correct answer: A

EAC = AC + (BAC - EV) assumes future work will be performed at the planned rate (ETC = BAC - EV), meaning today's variances are seen as one-time anomalies. When variances are expected to continue: use EAC = BAC / CPI. When re-estimating from scratch: use EAC = AC + ETC (new bottom-up estimate). When both CPI and SPI matter: use EAC = AC + [(BAC - EV) / (CPI × SPI)]. Choosing the right EAC formula depends on the management assumption about future performance.

Question 11 of 22

A project has PV = $450,000, EV = $500,000, AC = $480,000, BAC = $900,000. The project manager needs to report EAC assuming current efficiency continues. What is the EAC?

  1. A.$900,000
  2. B.$864,000
  3. C.$880,000
  4. D.$432,000
Show answer and explanation

Correct answer: B

CPI = EV / AC = $500,000 / $480,000 = 1.0417. EAC = BAC / CPI = $900,000 × ($480,000 / $500,000) = $864,000. The project is performing better than planned (CPI > 1), so the EAC is less than the BAC. An EAC equal to the BAC ignores the favorable cost performance to date, and $432,000 is far below the cost already incurred. With SPI = EV / PV = $500,000 / $450,000 = 1.11, the project is also ahead of schedule, a favorable position.

Question 12 of 22

A project manager is reporting to the sponsor. The project has: EV = $320,000, PV = $400,000, AC = $350,000, BAC = $800,000. Calculate the Variance at Completion (VAC) if the current CPI is expected to continue.

  1. A.VAC = -$75,000, meaning the project will exceed the budget by $75,000
  2. B.VAC = +$75,000, meaning the project will finish under budget
  3. C.VAC = -$75,714, meaning the project will exceed the budget by approximately $75,700
  4. D.VAC = $0, meaning the project will finish exactly on budget
Show answer and explanation

Correct answer: A

CPI = EV / AC = $320,000 / $350,000 = 0.9143. EAC = BAC / CPI = $800,000 × $350,000 / $320,000 = $875,000. VAC = BAC - EAC = $800,000 - $875,000 = -$75,000. A negative VAC means the project is forecasted to exceed its budget by $75,000. The -$75,714 figure comes from rounding errors in intermediate steps: using the exact CPI gives exactly -$75,000. A positive VAC has the wrong sign, and a VAC of $0 ignores the current cost overrun (CPI < 1). Key insight: VAC = BAC - EAC represents the expected cost overrun or underrun at project completion.

Question 13 of 22

During the monthly performance review of a predictive project, the project manager sees that EV is $80,000 and AC is $100,000 for the work completed to date. What does this MOST likely indicate?

  1. A.The project is over budget for the work done, with a CPI of 0.8 and CV of -$20,000.
  2. B.The project is behind schedule, with a schedule variance of -$20,000 for the reporting period.
  3. C.The project is under budget, showing a positive cost variance of $20,000 on the work performed.
  4. D.The project has a CPI of 1.25, earning $1.25 of value for each dollar it has spent on the work.
Show answer and explanation

Correct answer: A

With EV of $80,000 and AC of $100,000, CV = EV - AC = -$20,000 and CPI = EV / AC = 0.8, so the project is over budget for the work it has accomplished. Reading the gap as a schedule variance mixes up cost and schedule, because schedule variance compares EV with PV, not with AC. Calling it a positive $20,000 variance reverses the formula by subtracting EV from AC. A CPI of 1.25 comes from dividing AC by EV, which inverts the index and turns a cost problem into apparent efficiency.

Question 14 of 22

At the end of the third quarter, the performance report for a hybrid project shows an SPI of 0.85 and a CPI of 1.02. Which statement BEST describes the project's status?

  1. A.The project is over budget, earning only about 85 cents of value for each dollar actually spent.
  2. B.The project is ahead of schedule, delivering its planned work with fewer hours than were budgeted.
  3. C.Less work has been completed than planned to date, while costs are in line with the value earned.
  4. D.The critical path has slipped by 15%, and the final delivery date will be missed by that margin.
Show answer and explanation

Correct answer: C

SPI = EV / PV, so a value of 0.85 means only 85% of the work planned to date has been earned, while a CPI of 1.02 shows cost efficiency is on target. Treating 0.85 as cents of value per dollar spent describes CPI, not SPI, confusing schedule with cost. Reading an index below 1.0 as ahead of schedule inverts its meaning. SPI is a cost-weighted measure across all work and does not show whether the critical path has slipped, so the project manager needs the schedule network before predicting the end date.

Question 15 of 22

An agile team tracks its release with AgileEVM against a fixed release budget (BAC) of $600,000. For three consecutive sprints, the estimate at completion has trended upward and now stands at $680,000. What does this trend MOST likely indicate?

  1. A.The release is expected to finish later than planned, as its estimate at completion exceeds the BAC.
  2. B.If current cost performance continues, the release will cost more than its approved budget.
  3. C.The team has already spent more than the $600,000 BAC, and the remaining release work is unfunded.
  4. D.The release shows a positive variance at completion and should finish with part of its budget unspent.
Show answer and explanation

Correct answer: B

EAC is the expected total cost at completion based on performance so far, so an EAC of $680,000 against a BAC of $600,000 forecasts an overrun of about $80,000 if trends continue. EAC is a cost forecast and does not by itself say the release will finish late. EAC is not money already spent; actual cost to date is AC. VAC = BAC - EAC is -$80,000 here, so a negative variance means an overrun, not leftover budget.

Question 16 of 22

Two months ago, a predictive project's cumulative CPI was 0.82, and the project manager put corrective actions in place to cut rework. The latest report shows the cumulative CPI has risen to 0.95. What should the project manager conclude?

  1. A.The project is now under budget for the work performed, given that the cumulative CPI is rising.
  2. B.The schedule has recovered, with work now being finished close to the rate set in the project baseline.
  3. C.The project is now spending less money in each period than it did before the corrective action.
  4. D.Cost efficiency has improved since the action, but work still costs more than the value it earns.
Show answer and explanation

Correct answer: D

A rise in cumulative CPI from 0.82 to 0.95 shows that cost efficiency has improved, but a CPI below 1.0 still means each dollar spent earns less than a dollar of value. Calling the project under budget ignores that the index has not yet reached 1.0. CPI says nothing about schedule recovery, which is measured by SPI. CPI is a ratio of EV to AC, so it can improve even if spending per period stays the same or rises, provided more value is earned.

Question 17 of 22

A hybrid project has a BAC of $1.2 million. Using current cost performance, the project manager calculates an EAC of $1.35 million and reports a VAC of -$150,000 at the steering committee meeting. What does the negative VAC MOST likely indicate?

  1. A.The project has already spent $150,000 more than the value of the work completed so far.
  2. B.The project is forecast to finish about $150,000 over its originally approved budget.
  3. C.The project is forecast to finish $150,000 under budget, which can be released as savings.
  4. D.The estimate to complete the remaining work is $150,000, to be funded from management reserve.
Show answer and explanation

Correct answer: B

VAC = BAC - EAC, so $1.2 million minus $1.35 million gives -$150,000, a forecast overrun at completion. Money already spent beyond the value of completed work is the cost variance (EV - AC), not the VAC. Reading a negative VAC as savings flips the sign of the formula. The estimate to complete is EAC - AC, the cost of the remaining work, which is a different figure from the gap between the budget and the forecast.

Question 18 of 22

Midway through an agile project with a fixed budget, the project manager calculates a TCPI based on BAC of 1.35, while the cumulative CPI to date has been 0.88. What does this MOST likely indicate?

  1. A.Staying within the original budget would require cost efficiency far better than achieved so far.
  2. B.The team is now earning about $1.35 of value for each dollar spent, well ahead of its cost plan.
  3. C.The remaining work should come in under budget, since a TCPI above 1.0 reflects strong efficiency.
  4. D.The team must deliver its remaining features about 35% faster than planned to meet the release date.
Show answer and explanation

Correct answer: A

TCPI = (BAC - EV) / (BAC - AC) is the cost efficiency needed on the remaining work to finish within the budget. A TCPI of 1.35 against a CPI of 0.88 means the team would have to become far more efficient than it has been, which is rarely realistic and signals that the BAC is likely not achievable. Reading 1.35 as value earned per dollar confuses TCPI with CPI. A TCPI above 1.0 is a warning, not evidence of strong efficiency, and the index concerns cost, not delivery speed.

Question 19 of 22

A predictive project's status report shows a PV of $250,000, an EV of $250,000, and an AC of $290,000. Which conclusion is BEST supported by these figures?

  1. A.The project is both behind schedule and over budget, with AC exceeding the planned value to date.
  2. B.Cost is on plan because EV equals PV, but the schedule is slipping by about $40,000 of work.
  3. C.Performance is on track overall, as earned value matches the plan and spending reflects the work.
  4. D.The schedule is on plan, but the completed work has cost about $40,000 more than its earned value.
Show answer and explanation

Correct answer: D

SV = EV - PV = $0 and SPI = 1.0, so the schedule is on plan, while CV = EV - AC = -$40,000 and CPI is about 0.86, so cost performance is poor. Comparing AC with PV to judge the schedule confuses actual cost with planned value. Treating EV equal to PV as a cost measure swaps the cost and schedule formulas. Saying performance is on track overlooks that the project spent $290,000 to earn $250,000 of value.

Question 20 of 22

On a hybrid project, a work package with a budget of $40,000 is reported as 50% complete, yet $32,000 has been spent on it. What should the project manager conclude?

  1. A.The work package is 30% behind schedule, based on budget spent versus work done.
  2. B.Spending often runs ahead of progress at the midpoint, and the variance should even out by the end.
  3. C.The work package has a CPI of about 0.63, and the cause of the overrun should be investigated.
  4. D.A change request should raise the work package budget to cover the overrun that has occurred so far.
Show answer and explanation

Correct answer: C

The work package has earned $20,000 of value (50% of $40,000) at a cost of $32,000, so CPI = EV / AC is about 0.63 and CV is -$12,000. That is a significant cost problem, and the project manager should find its cause before choosing a response. The gap between percent spent and percent complete is a cost measure, not a schedule variance, which would need the planned value. Assuming the variance will even out ignores the evidence, and asking for more budget before understanding the cause skips root cause analysis.

Question 21 of 22

Midway through an agile release, the sponsor and product owner approve adding a payments module that raises the release budget by $150,000. The project manager notes that the EAC still reflects the original release scope and budget. What should the project manager do NEXT?

  1. A.Update the release baseline (PV and BAC) for the payments module, then recompute EAC from current CPI.
  2. B.Keep reporting EAC against the original BAC, showing the added payments module as a cost overrun.
  3. C.Reset the cumulative CPI to 1.0 and forecast the larger release as if past sprint results did not apply.
  4. D.Review the revised release forecast with the sponsor before the baseline is updated for the new module.
Show answer and explanation

Correct answer: A

An approved change becomes part of the baseline, so the planned value and BAC must include the payments module before forecasts mean anything. EAC should then be recalculated using that new baseline and the actual cost performance observed so far. Reporting against the old BAC shows approved scope as an overrun, which misleads stakeholders. Resetting CPI throws away real performance data, and presenting a forecast to the sponsor before the baseline is updated puts the steps in the wrong order.

Question 22 of 22

Halfway through the planned schedule of a predictive project with a $1 million BAC, the sponsor notes that only $400,000 has been spent against $500,000 of planned value and asks the project manager to confirm that the project is under budget. How should the project manager respond?

  1. A.Confirm that the project is under budget, as the $400,000 spent is less than the $500,000 planned to date.
  2. B.Explain that the project is behind schedule, since only 40% of the budget has been spent at the midpoint.
  3. C.Report the remaining $600,000 of the $1 million BAC as the estimate to complete the project.
  4. D.Explain to the sponsor that spend must be compared with the earned value of the work done before judging.
Show answer and explanation

Correct answer: D

Actual cost alone cannot show cost or schedule performance; it must be compared with the earned value of completed work (CPI = EV / AC) and the planned value (SPI = EV / PV). If, for example, only $300,000 of value had been earned, the project would be both over budget and behind schedule despite the low spend. Comparing AC with PV treats planned value as a cost benchmark, and using AC to judge schedule confuses actual cost with progress. BAC - AC is not the estimate to complete unless future work goes exactly to plan, and it ignores performance to date.

Ready for exam conditions?

Practice these questions with randomized answer order and instant scoring, or take a full domain-weighted mock exam with a real exam timer.

More Process practice questions