Question 1 of 12
Your project has a BAC of $500,000. At the status date, the EV is $200,000 and the AC is $250,000. What does this tell you about project performance?
- A.The project is over budget for the work completed
- B.The project is under budget and ahead of schedule
- C.The project has spent more than the planned budget allocation
- D.The project is on schedule but has scope issues
Show answer and explanation
Correct answer: A
Cost Performance Index (CPI) = EV / AC = 200,000 / 250,000 = 0.8. A CPI < 1 means you are spending more than the value earned — the project is over budget. We cannot determine schedule performance without PV. The project has not necessarily overspent its total budget — it is over budget for work completed to date.