PMPRocket
PMP Practice QuestionsRisk Management
Process Domain

Risk Management PMP Practice Questions

Test yourself with 24 free, scenario-based PMP practice questions on risk management, drawn from the Process domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Study first: PMP formulas cheat sheet · how to answer PMP situational questions

Question 1 of 24

During sprint planning, the team identifies that a critical API integration may not be available on time from a third-party vendor. What is the BEST way to handle this risk?

  1. A.Ignore the risk until the vendor confirms the delay — planning responses to unconfirmed third-party risks creates overhead without confirmed probability or impact data to justify the effort.
  2. B.Escalate to the product owner and halt sprint planning until the vendor confirms availability — committing to a sprint without resolving this dependency creates a commitment the team cannot reliably keep.
  3. C.Add the risk to the risk register, plan a mitigation strategy such as building a mock API, and add a contingency plan.
  4. D.Remove the integration story from the backlog until the vendor confirms availability — planning work with an unconfirmed external dependency creates a sprint commitment that cannot be reliably fulfilled.
Show answer and explanation

Correct answer: C

Proactive risk management requires documenting the risk, planning mitigation (e.g., mock API to continue development), and contingency if it materializes. Ignoring is passive acceptance with no plan. Stopping planning is an overreaction. Removing the story avoids the risk but delays value delivery unnecessarily.

Question 2 of 24

During risk identification, a project manager learns that a key subcontractor may go bankrupt within the project timeline. The probability is 15% and the financial impact would be $400,000. What is the Expected Monetary Value (EMV) of this risk?

  1. A.$400,000
  2. B.$340,000
  3. C.$415,000
  4. D.$60,000
Show answer and explanation

Correct answer: D

Expected Monetary Value (EMV) = Probability × Impact = 0.15 × $400,000 = $60,000. EMV represents the average outcome if the risk scenario were to play out many times. This $60,000 should be included in the project's contingency reserve as part of quantitative risk analysis. The full $400,000 would only apply if the risk were certain. EMV is used in decision tree analysis and Monte Carlo simulations to quantify risk exposure.

Question 3 of 24

A risk register entry shows: Probability = High (0.7), Impact = High (0.8). The probability-impact score is 0.56. According to the probability-impact matrix, how should this risk be prioritized?

  1. A.High priority — a P×I score of 0.56 is in the red zone requiring immediate active response planning
  2. B.Low priority — only 56% of risks require active management
  3. C.Medium priority — the score should be compared to the organization's risk threshold
  4. D.The risk should be accepted since the probability-impact matrix is only used for low-probability risks
Show answer and explanation

Correct answer: A

A P×I score of 0.56 (High × High) places this risk firmly in the highest priority zone of the probability-impact matrix. Most organizations set their 'red zone' threshold at scores above 0.40 or 0.50. This risk requires immediate active response planning — avoid, mitigate, transfer, or exploit depending on whether it is a threat or opportunity. The risk register should include the assigned risk owner and specific response actions. This is not a medium or low priority risk.

Question 4 of 24

A project manager identifies a risk that a key technology vendor may raise prices by 20% mid-project. The project manager negotiates a fixed-price agreement with the vendor before the project starts. Which risk response strategy is this?

  1. A.Mitigate — the probability of the price increase is reduced
  2. B.Transfer — the financial risk is shifted to the vendor through the fixed-price contract
  3. C.Accept — the team acknowledges the risk and does nothing proactive
  4. D.Avoid — the risk is eliminated by changing the procurement approach
Show answer and explanation

Correct answer: B

Using a fixed-price contract transfers the risk of price increases to the vendor. The buyer is now shielded from cost escalation — if prices rise, the vendor absorbs the difference. Transfer does not eliminate the risk but shifts its financial consequence to a third party (often through contracts or insurance). Mitigation reduces probability or impact but does not transfer ownership. Avoidance eliminates the risk entirely. Acceptance takes no proactive action.

Question 5 of 24

An agile team discovers a significant technical risk during a sprint that could prevent delivery of the highest-priority feature. The risk was not on the risk register. What should the team do FIRST?

  1. A.Stop the sprint, notify the product owner, and wait for direction
  2. B.Continue the sprint and document the risk in the retrospective
  3. C.Add the risk to the risk register, assess its impact
  4. D.Escalate to senior management now without discussing with the product owner
Show answer and explanation

Correct answer: C

Agile teams practice continuous risk management. The team should immediately add the risk to the risk register and assess it. If it threatens the sprint goal, the product owner must be informed without delay — not just at the next standup — so backlog adjustments can be made. Stopping the sprint is premature without first understanding the impact. Deferring to the retrospective ignores an active threat. Bypassing the product owner to go to senior management violates the agile communication structure.

Question 6 of 24

A project manager is developing risk responses for a threat with probability 0.5 and impact of $200,000. A mitigation action costs $40,000 and would reduce the probability to 0.2. Should the mitigation be implemented based on EMV analysis?

  1. A.Yes — the mitigation cost of $40,000 is less than the original EMV of $100,000
  2. B.No — the residual EMV after mitigation ($40,000) plus the mitigation cost ($40,000) equals the original EMV ($100,000), making it neutral.
  3. C.No — mitigation is only appropriate for high-probability, high-impact risks
  4. D.Yes — the mitigation saves $60,000 in EMV reduction minus the $40,000 cost, yielding a net benefit of $20,000
Show answer and explanation

Correct answer: D

Original EMV = 0.5 × $200,000 = $100,000. After mitigation, EMV = 0.2 × $200,000 = $40,000. EMV reduction = $100,000 - $40,000 = $60,000 saved. Mitigation cost = $40,000. Net benefit = $60,000 - $40,000 = $20,000. Since the mitigation saves more than it costs, it should be implemented. This is a cost-benefit analysis of risk responses — a core quantitative risk management technique. Comparing only the mitigation cost with the original EMV ignores the residual risk, and the claim that the response is neutral miscounts the residual EMV.

Question 7 of 24

A project manager is planning a complex hybrid project. The risk register has 45 risks. Which approach to risk monitoring is MOST appropriate?

  1. A.Focus active monitoring on the top 10 risks by P×I score, and reassess the full register monthly or at major phase gates.
  2. B.Review all 45 risks weekly with the full project team
  3. C.Delegate all risk monitoring to individual risk owners and only review when an issue is escalated
  4. D.Archive risks after the planning phase and only revisit if a risk materializes
Show answer and explanation

Correct answer: A

Effective risk monitoring focuses effort on the highest-priority risks. Reviewing all 45 risks weekly is impractical and reduces meeting efficiency. The top risks by P×I score should be tracked actively, while lower-priority risks are reviewed on a regular cadence (monthly or at phase gates). Full delegation without oversight creates accountability gaps. Archiving risks after planning violates continuous risk management principles — new risks emerge throughout the project.

Question 8 of 24

A risk register entry identifies a threat with the following response options. Which THREE are valid negative risk response strategies according to PMBOK?

Select all that apply.

  1. A.Transfer — shift the financial consequence of the risk to a third party
  2. B.Mitigate — reduce the probability or impact of the risk to an acceptable level
  3. C.Enhance — increase the probability or positive impact of an opportunity
  4. D.Avoid — change the project plan to eliminate the risk or its impact entirely
  5. E.Exploit — ensure the opportunity is realized by taking deliberate action
Show answer and explanation

Correct answers: A and B and D

The strategies for negative risks (threats) are escalate, avoid, transfer, mitigate and accept. Transfer shifts the consequence to a third party, mitigate reduces probability or impact, and avoid changes the plan to eliminate the threat. Exploit and enhance are strategies for positive risks (opportunities): exploit makes sure the opportunity happens, and enhance increases its probability or impact.

Question 9 of 24

A project manager is performing quantitative risk analysis. The Monte Carlo simulation results show a 10% probability of completing the project by the target date, and an 80% confidence completion date is 6 weeks later. What action should the project manager take?

  1. A.Re-run the simulation with more optimistic probability distributions — adjusting the input ranges toward best-case scenarios will produce results that better support the current schedule commitment.
  2. B.Present the simulation results to the sponsor and recommend adjusting the project deadline or scope to achieve a higher confidence level.
  3. C.Accept the 10% probability and proceed — Monte Carlo simulations are often overly conservative and do not account for the team's ability to actively manage and mitigate risks during execution.
  4. D.Eliminate the highest-probability risks and re-run the simulation — removing these risks from the model will increase the confidence interval and demonstrate a higher likelihood of meeting the deadline.
Show answer and explanation

Correct answer: B

A 10% probability of meeting the target date is extremely low — the project has a 90% chance of being late. The project manager must present these findings transparently to the sponsor and recommend adjustments: extend the deadline, reduce scope, add resources, or increase contingency reserves. Manipulating assumptions to get better numbers is unethical. Accepting a 10% probability without escalation is irresponsible. Eliminating risks from analysis distorts results.

Question 10 of 24

A project manager is conducting a risk workshop for a hybrid project. The team identifies 30 risks in 2 hours. The project manager wants to prioritize which risks deserve detailed response planning. What tool should be used next?

  1. A.Monte Carlo simulation — to quantify the cumulative probability impact of all 30 risks simultaneously and generate a probabilistic distribution of project schedule and cost outcomes.
  2. B.Failure Mode and Effects Analysis (FMEA) — to evaluate each risk's failure modes, severity, and likelihood in a structured format that prioritizes the most urgent responses.
  3. C.Probability-impact matrix — to quickly score each risk and focus detailed planning on high-priority risks
  4. D.Decision tree analysis — to evaluate the expected financial value of each response option and support informed trade-offs between different mitigation and contingency strategies.
Show answer and explanation

Correct answer: C

After risk identification, qualitative risk analysis using the probability-impact matrix is the first step to prioritize risks. Each risk is scored on probability and impact, placing it in low, medium, or high zones. High-priority risks receive detailed response planning; low-priority risks may be accepted with watch-list monitoring. This ensures effort is focused where it matters most. Monte Carlo and decision trees are quantitative tools used after qualitative prioritization. FMEA is used in manufacturing quality contexts.

Question 11 of 24

A risk response plan has been implemented for a key project risk. Which THREE activities are part of ongoing risk monitoring?

Select all that apply.

  1. A.Removing all risks from the register once their response plans are implemented
  2. B.Identifying new risks that emerge as the project environment changes
  3. C.Re-baselining the schedule every time a risk trigger is observed
  4. D.Tracking risk triggers to determine if a risk is about to materialize
  5. E.Reassessing the probability and impact of risks as the project progresses
Show answer and explanation

Correct answers: B and D and E

Ongoing risk monitoring includes tracking risk triggers (early warning signs that a risk is about to occur), reassessing the probability and impact of risks as new information appears, and identifying new risks, since risk identification is continuous. It also includes evaluating how well implemented responses work. Risks should not be removed from the register just because a response is in place: they stay open until they are resolved, expire or occur. Seeing a trigger calls for the planned response, not a new schedule baseline, which needs approved changes.

Question 12 of 24

In a hybrid construction project, site work is scheduled to start in six weeks. During a coordination call, the team learns that a key supplier, which is contractually responsible for permits, may not obtain them in time. The issue is not in the risk register. What should the project manager do FIRST?

  1. A.Direct procurement to start qualifying a second supplier for the site work while the current supplier keeps pursuing the permits.
  2. B.Log the permit delay in the risk register and analyze its probability and schedule impact together with the supplier.
  3. C.Draw on the contingency reserve now to cover the site work delay that the late permits are expected to cause.
  4. D.Let the supplier assess the permit delay on its own and report the probability and impact at the next monthly supplier review.
Show answer and explanation

Correct answer: B

The permit problem is a newly identified threat, so the first step is to record it and analyze how likely it is and what it would do to the site work schedule, drawing on the supplier's knowledge. Only then can the team choose a proportionate response. Qualifying a second supplier may become a sensible response, but committing procurement effort before the risk is understood is premature. Drawing on contingency reserve now assumes the delay will happen and skips analysis. Leaving the assessment to the supplier until a monthly review hands off a threat to the project's own schedule and delays analysis when site work is only six weeks away.

Question 13 of 24

An agile team is migrating customer records to a new platform. Over the last two sprints, defects in the migration scripts have kept piling up, and the team now believes the chance of a failed cutover is rising. What is the MOST appropriate action for the project manager?

  1. A.Agree with the product owner to schedule a hardening sprint just before go-live and fix all the migration defects there.
  2. B.Tell the developers to pause feature stories today and clear every open migration defect before taking new backlog items.
  3. C.Raise the rising cutover risk with the team and product owner so migration fixes and a trial migration get ranked in the backlog.
  4. D.Raise the probability score in the risk register and review the migration risk with the steering group at its next monthly meeting.
Show answer and explanation

Correct answer: C

In agile, risk responses are handled as work in the backlog, and the product owner decides its priority with the team's input. Making the rising cutover risk visible so fixes and a trial migration are ranked appropriately addresses it early and transparently. Agreeing with the product owner on a hardening sprint just before go-live still defers the response until the risk is hardest to manage. Telling developers to drop feature work bypasses the product owner's prioritization. Updating the score and reviewing it at a monthly steering meeting records the change but delays any real response.

Question 14 of 24

During execution of a predictive manufacturing project, an engineer reports that a new automated inspection tool could cut the cycle time of a key production step by 20 percent if the team adopts it within the next month. The schedule baseline is approved. What should the project manager do FIRST?

  1. A.Analyze the tool's cost, benefit, and schedule effect as an opportunity before proposing any change to the baseline.
  2. B.Authorize the engineer to buy and install the inspection tool right away and record the gain in the next status report.
  3. C.Submit a change request now and let the change control board analyze the tool's cost and schedule effect at its next meeting.
  4. D.Add the inspection tool to the lessons learned register and keep the approved baseline unchanged.
Show answer and explanation

Correct answer: A

Opportunities are managed like threats: they are identified and analyzed before a response such as exploit or enhance is chosen. Understanding the tool's real cost, benefit, and schedule effect comes first and gives any later change request a solid basis. Buying the tool immediately bypasses analysis and change control on an approved baseline. A change request is likely needed later, but submitting it now and leaving the analysis to the board puts the work in the wrong order and wastes the board's time. Deferring the idea to lessons learned throws away a time-bound opportunity for this project.

Question 15 of 24

A hybrid project is building a customer portal. The team learns that a data privacy bill now in the legislature, which may pass within three months, could change how one of the portal's deliverables stores personal data. What should the project manager do FIRST?

  1. A.Have the team redesign the deliverable's data storage now to meet the requirements in the proposed bill.
  2. B.Record the bill in the risk register as an accepted risk and submit a change request only if it is eventually passed.
  3. C.Request that the sponsor assess the bill's impact with the legal department and decide whether the deliverable should go ahead.
  4. D.Assess the bill's likely impact on the deliverable together with the organization's compliance experts.
Show answer and explanation

Correct answer: D

Proposed legislation is an uncertain future event, so it should be treated as a risk, and the first step is for the project to assess its likely effect on the deliverable with people who understand the law. That assessment supports a proportionate response planned in time. Redesigning now commits effort to requirements that may change or never apply. Logging it as accepted and acting only once the bill passes skips the assessment and may leave too little time to respond. Handing the assessment and a go or no-go decision to the sponsor escalates something the project team can still analyze and manage itself.

Question 16 of 24

An agile team is considering a cloud messaging service that is still in beta. It could simplify the architecture considerably, but its instability could also delay the planned deployment. Nobody on the team has used it before. How should the project manager BEST handle this uncertainty?

  1. A.Encourage the team to adopt the beta service across the architecture now and handle any instability as it appears.
  2. B.Work with the product owner to add a time-boxed spike that tests the beta service before the team commits to it.
  3. C.Agree with the product owner to rule out the beta service and keep the current architecture as planned.
  4. D.Log the beta service as a threat in the risk register and have the architect evaluate its stability at each release.
Show answer and explanation

Correct answer: B

The uncertainty cuts both ways and the team lacks knowledge, so the best way to handle it is to reduce the uncertainty cheaply. A time-boxed spike, prioritized with the product owner, produces evidence to decide whether to exploit the opportunity or avoid the threat. Adopting it everywhere accepts the deployment threat without learning anything. Ruling it out, even with the product owner's agreement, discards a possible opportunity based on assumptions. Logging it only as a threat and evaluating it release by release ignores the upside and learns too late to shape the architecture.

Question 17 of 24

In a predictive project, a critical interface is being delivered by another division. After an organizational restructuring, that division's team lead has left, and status reports on the interface have stopped. Integration testing is two months away. What should the project manager do FIRST?

  1. A.Have the project team start building the interface in-house to remove the dependency on the restructured division.
  2. B.Escalate to the sponsor and ask them to direct the restructured division to restore its commitment to the interface.
  3. C.Contact the division's new management to confirm whether the interface commitment still stands.
  4. D.Reassess the integration schedule risk and add a time buffer to the testing activities in the schedule baseline.
Show answer and explanation

Correct answer: C

The project manager does not yet know whether the dependency is actually at risk, only that information has stopped. Reaching the division's new management to confirm whether the commitment still stands provides the facts every other decision depends on. Building the interface in-house is a costly response chosen without facts. Escalating to the sponsor is appropriate only if the project manager cannot resolve the matter directly. Reassessing the schedule risk without first learning the division's position rests on guesswork, and adding a buffer to the baseline would also bypass change control.

Question 18 of 24

On a hybrid project, a risk of rising software license fees was on the watch list. After the vendor announced a pricing review, the risk owner reanalyzed it: it now ranks among the top five risks, and the likely fee increase across four work packages exceeds the remaining contingency reserve. The vendor has offered to lock current rates in a multi-year license if it is signed before the review closes. What is the BEST response?

  1. A.Note the vendor's rate-lock offer in the risk register and revisit it once the final prices are published.
  2. B.Draw on management reserve to cover the fee increase and inform the sponsor once the new prices have taken effect.
  3. C.Split the expected fee increase across the four work packages and have each owner absorb its share.
  4. D.Get sponsor approval for the multi-year commitment and sign the vendor's rate-lock license through procurement.
Show answer and explanation

Correct answer: D

The analysis is done and shows a high-priority threat the contingency reserve cannot absorb, so a concrete response is needed now. Locking current rates through the vendor's offer, with sponsor approval for a commitment that outlasts the project and through the organization's procurement process, removes most of the exposure before it materializes. Recording the offer and waiting for final prices ignores the reanalysis and lets a time-bound offer lapse. Management reserve is not the project manager's to spend without approval, and informing the sponsor afterward reverses the proper order. Splitting the increase across work packages hides the combined impact instead of reducing it.

Question 19 of 24

In an agile project, the risks recorded on the team's board each have an owner from the development team. At a review, the project manager notices that none of the owners has updated their response actions for over a month. What should the project manager do FIRST?

  1. A.Talk with the risk owners to learn why updates stopped and agree how risk review fits into the team's sprint events.
  2. B.Reassign every risk on the board to the project manager and keep all of the response actions current personally.
  3. C.Report the inactive risk owners to their functional managers and add risk updates to their appraisal goals.
  4. D.Review all response actions personally using the latest sprint review and update the board on the owners' behalf.
Show answer and explanation

Correct answer: A

Stale risk updates are a symptom, and the project manager should first understand the cause, such as overload or unclear expectations, before deciding what to change. Agreeing with the owners on how risk review fits into existing sprint events addresses the root cause and keeps ownership with the team. Taking over all risks centralizes work that the team is better placed to do. Reporting owners to their managers damages trust before anyone has asked what went wrong. Reviewing and updating the actions on the owners' behalf fixes the board once but leaves the underlying problem unaddressed.

Question 20 of 24

Early in a predictive project, the threat of equipment theft at a construction site was mitigated by hiring a security firm. The staging area has since moved to a new location. The risk owner has reassessed the theft risk there and found that the unfenced perimeter and a separate, uncontrolled access road are now the main exposures. What should the project manager do NEXT?

  1. A.Close the theft risk in the risk register and keep the security firm's current contract running on its original terms.
  2. B.Have the security firm review the new staging area again during its next quarterly site audit.
  3. C.Update the theft response to fence the staging area and control the access road, then adjust the security contract.
  4. D.Insure the equipment at the new staging area and defer the fencing and road controls to the next project phase.
Show answer and explanation

Correct answer: C

The reassessment is already done and pinpoints the fencing gap and the uncontrolled road, so the next step is to update the response to address those specific exposures and align the security contract with it. Closing the risk assumes the old mitigation still works at a site it was never designed for. Another review at a quarterly audit repeats analysis that is complete and leaves the exposure open in the meantime. Insuring the equipment and deferring the fencing and road controls compensates for losses but leaves the identified weaknesses open now, when thefts could still delay the work.

Question 21 of 24

A hybrid project's approved response for a liability risk was to transfer it through an insurance policy. The insurer has now withdrawn coverage for this type of work, and the risk owner has flagged that the response can no longer be carried out. What should the project manager do NEXT?

  1. A.Work with the risk owner to evaluate alternative responses and route any resulting plan changes through change control.
  2. B.Keep the insurance transfer as approved and work with the risk owner to press the insurer to reinstate the withdrawn coverage.
  3. C.Change the response to passive acceptance in the risk register and note the insurer's withdrawal as the reason.
  4. D.Refer the liability risk to the steering committee to evaluate alternative responses and choose the one the team adopts.
Show answer and explanation

Correct answer: A

An approved response that can no longer be carried out must be revisited, and the risk owner is the right person to help evaluate alternatives such as another insurer, contract terms, or mitigation, with any resulting plan changes going through change control. Working with the risk owner to keep pressing the insurer relies on a response that no longer exists instead of planning a workable one. Switching to passive acceptance without analysis may leave a significant liability uncovered. Referring the evaluation and choice to the steering committee shifts a decision that is within the project's authority and sidelines the risk owner.

Question 22 of 24

Which THREE outputs or uses are most associated with deeper quantitative risk analysis?

Select all that apply.

  1. A.Eliminating the need for management reserves
  2. B.Estimating the probability of meeting a target date or cost
  3. C.Using tornado diagrams to understand sensitivity drivers
  4. D.Replacing all qualitative analysis so prioritization is faster
  5. E.Using probability distributions to model uncertainty
Show answer and explanation

Correct answers: B and C and E

Quantitative analysis deepens decision support by modeling uncertainty and confidence levels. It complements, rather than replaces, qualitative analysis and does not eliminate the need for reserves.

Question 23 of 24

A Monte Carlo output shows only a 20% chance of meeting the sponsor's target date. What should the project manager do FIRST?

  1. A.Withhold the simulation results from the sponsor — sharing probabilistic models with stakeholders not trained in statistics creates confusion and may undermine confidence in the project without good reason.
  2. B.Discard the simulation result as too theoretical — Monte Carlo outputs represent modeled scenarios rather than actual conditions, and experienced PMs rely on their judgment over statistical models.
  3. C.Commit to the target date anyway to maintain sponsor confidence — demonstrating certainty is a leadership responsibility, and expressing probabilistic uncertainty undermines the team's credibility.
  4. D.Communicate the finding transparently and discuss options such as scope trade-offs, schedule change, added contingency, or risk response improvements.
Show answer and explanation

Correct answer: D

A low confidence date is decision support, not an embarrassment. The right response is transparent discussion of options, not suppression of the result.

Question 24 of 24

A project manager is comparing two response strategies for a major uncertainty with different probabilities and financial outcomes. Which tool is MOST suitable?

  1. A.RACI matrix
  2. B.Burndown chart
  3. C.Decision tree analysis
  4. D.Stakeholder engagement matrix
Show answer and explanation

Correct answer: C

Decision trees help compare options when probabilities and consequences differ across branches of choice.

Ready for exam conditions?

Practice these questions with randomized answer order and instant scoring, or take a full domain-weighted mock exam with a real exam timer.

More Process practice questions