PMPRocket
PMP Practice QuestionsRisk Management
Process Domain

Risk Management PMP Practice Questions

Test yourself with 21 free, scenario-based PMP practice questions on risk management, drawn from the Process domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Question 1 of 21

During sprint planning, the team identifies that a critical API integration may not be available on time from a third-party vendor. What is the BEST way to handle this risk?

  1. A.Ignore the risk until the vendor confirms the delay — planning responses to unconfirmed third-party risks creates overhead without confirmed probability or impact data to justify the effort.
  2. B.Escalate to the product owner and halt sprint planning until the vendor confirms availability — committing to a sprint without resolving this dependency creates a commitment the team cannot reliably keep.
  3. C.Add the risk to the risk register, plan a mitigation strategy such as building a mock API, and add a contingency plan.
  4. D.Remove the integration story from the backlog until the vendor confirms availability — planning work with an unconfirmed external dependency creates a sprint commitment that cannot be reliably fulfilled.
Show answer and explanation

Correct answer: C

Proactive risk management requires documenting the risk, planning mitigation (e.g., mock API to continue development), and contingency if it materializes. Ignoring is passive acceptance with no plan. Stopping planning is an overreaction. Removing the story avoids the risk but delays value delivery unnecessarily.

Question 2 of 21

During risk identification, a project manager learns that a key subcontractor may go bankrupt within the project timeline. The probability is 15% and the financial impact would be $400,000. What is the Expected Monetary Value (EMV) of this risk?

  1. A.$400,000
  2. B.$340,000
  3. C.$415,000
  4. D.$60,000
Show answer and explanation

Correct answer: D

Expected Monetary Value (EMV) = Probability × Impact = 0.15 × $400,000 = $60,000. EMV represents the average outcome if the risk scenario were to play out many times. This $60,000 should be included in the project's contingency reserve as part of quantitative risk analysis. The full $400,000 would only apply if the risk were certain. EMV is used in decision tree analysis and Monte Carlo simulations to quantify risk exposure.

Question 3 of 21

A risk register entry shows: Probability = High (0.7), Impact = High (0.8). The probability-impact score is 0.56. According to the probability-impact matrix, how should this risk be prioritized?

  1. A.High priority — a P×I score of 0.56 is in the red zone requiring immediate active response planning
  2. B.Low priority — only 56% of risks require active management
  3. C.Medium priority — the score should be compared to the organization's risk threshold
  4. D.The risk should be accepted since the probability-impact matrix is only used for low-probability risks
Show answer and explanation

Correct answer: A

A P×I score of 0.56 (High × High) places this risk firmly in the highest priority zone of the probability-impact matrix. Most organizations set their 'red zone' threshold at scores above 0.40 or 0.50. This risk requires immediate active response planning — avoid, mitigate, transfer, or exploit depending on whether it is a threat or opportunity. The risk register should include the assigned risk owner and specific response actions. This is not a medium or low priority risk.

Question 4 of 21

A project manager identifies a risk that a key technology vendor may raise prices by 20% mid-project. The project manager negotiates a fixed-price agreement with the vendor before the project starts. Which risk response strategy is this?

  1. A.Mitigate — the probability of the price increase is reduced
  2. B.Transfer — the financial risk is shifted to the vendor through the fixed-price contract
  3. C.Accept — the team acknowledges the risk and does nothing proactive
  4. D.Avoid — the risk is eliminated by changing the procurement approach
Show answer and explanation

Correct answer: B

Using a fixed-price contract transfers the risk of price increases to the vendor. The buyer is now shielded from cost escalation — if prices rise, the vendor absorbs the difference. Transfer does not eliminate the risk but shifts its financial consequence to a third party (often through contracts or insurance). Mitigation reduces probability or impact but does not transfer ownership. Avoidance eliminates the risk entirely. Acceptance takes no proactive action.

Question 5 of 21

An agile team discovers a significant technical risk during a sprint that could prevent delivery of the highest-priority feature. The risk was not on the risk register. What should the team do FIRST?

  1. A.Stop the sprint, notify the product owner, and wait for direction
  2. B.Continue the sprint and document the risk in the retrospective
  3. C.Add the risk to the risk register, assess its impact
  4. D.Escalate to senior management now without discussing with the product owner
Show answer and explanation

Correct answer: C

Agile teams practice continuous risk management. The team should immediately add the risk to the risk register and assess it. If it threatens the sprint goal, the product owner must be informed without delay — not just at the next standup — so backlog adjustments can be made. Stopping the sprint is premature without first understanding the impact. Deferring to the retrospective ignores an active threat. Bypassing the product owner to go to senior management violates the agile communication structure.

Question 6 of 21

A project manager is developing risk responses for a threat with probability 0.5 and impact of $200,000. A mitigation action costs $40,000 and would reduce the probability to 0.2. Should the mitigation be implemented based on EMV analysis?

  1. A.Yes — the mitigation cost of $40,000 is less than the original EMV of $100,000
  2. B.No — the residual EMV after mitigation ($40,000) plus the mitigation cost ($40,000) equals the original EMV ($100,000), making it neutral.
  3. C.No — mitigation is only appropriate for high-probability, high-impact risks
  4. D.Yes — the mitigation saves $60,000 in EMV reduction minus the $40,000 cost, yielding a net benefit of $20,000
Show answer and explanation

Correct answer: D

Original EMV = 0.5 × $200,000 = $100,000. After mitigation, EMV = 0.2 × $200,000 = $40,000. EMV reduction = $100,000 - $40,000 = $60,000 saved. Mitigation cost = $40,000. Net benefit = $60,000 - $40,000 = $20,000. Since the mitigation saves more than it costs, it should be implemented. This is a cost-benefit analysis of risk responses — a core quantitative risk management technique. this option incorrectly ignores the net benefit.

Question 7 of 21

A project manager is planning a complex hybrid project. The risk register has 45 risks. Which approach to risk monitoring is MOST appropriate?

  1. A.Focus active monitoring on the top 10 risks by P×I score, and reassess the full register monthly or at major phase gates.
  2. B.Review all 45 risks weekly with the full project team
  3. C.Delegate all risk monitoring to individual risk owners and only review when an issue is escalated
  4. D.Archive risks after the planning phase and only revisit if a risk materializes
Show answer and explanation

Correct answer: A

Effective risk monitoring focuses effort on the highest-priority risks. Reviewing all 45 risks weekly is impractical and reduces meeting efficiency. The top risks by P×I score should be tracked actively, while lower-priority risks are reviewed on a regular cadence (monthly or at phase gates). Full delegation without oversight creates accountability gaps. Archiving risks after planning violates continuous risk management principles — new risks emerge throughout the project.

Question 8 of 21

A risk register entry identifies a threat with the following response options. Which THREE are valid negative risk response strategies according to PMBOK?

Select all that apply.

  1. A.Transfer — shift the financial consequence of the risk to a third party
  2. B.Mitigate — reduce the probability or impact of the risk to an acceptable level
  3. C.Accept — acknowledge the risk and either set aside contingency or take no action
  4. D.Avoid — change the project plan to eliminate the risk or its impact entirely
  5. E.Exploit — ensure the opportunity is realized by taking deliberate action
Show answer and explanation

Correct answers: A and B and D

The four strategies for negative risks (threats) are: Avoid — eliminate the risk by changing plans; Transfer — shift consequences to a third party via insurance or contracts; Mitigate — reduce probability or impact; and Accept (E). Exploit is a positive risk (opportunity) strategy — it is the opposite of avoid and is used to ensure an opportunity is captured. The question asks only for three of the threat strategies, excluding accept. A, C, and D are the three strategies that require proactive planning.

Question 9 of 21

A project manager is performing quantitative risk analysis. The Monte Carlo simulation results show a 10% probability of completing the project by the target date, and an 80% confidence completion date is 6 weeks later. What action should the project manager take?

  1. A.Re-run the simulation with more optimistic probability distributions — adjusting the input ranges toward best-case scenarios will produce results that better support the current schedule commitment.
  2. B.Present the simulation results to the sponsor and recommend adjusting the project deadline or scope to achieve a higher confidence level.
  3. C.Accept the 10% probability and proceed — Monte Carlo simulations are often overly conservative and do not account for the team's ability to actively manage and mitigate risks during execution.
  4. D.Eliminate the highest-probability risks and re-run the simulation — removing these risks from the model will increase the confidence interval and demonstrate a higher likelihood of meeting the deadline.
Show answer and explanation

Correct answer: B

A 10% probability of meeting the target date is extremely low — the project has a 90% chance of being late. The project manager must present these findings transparently to the sponsor and recommend adjustments: extend the deadline, reduce scope, add resources, or increase contingency reserves. Manipulating assumptions to get better numbers is unethical. Accepting a 10% probability without escalation is irresponsible. Eliminating risks from analysis distorts results.

Question 10 of 21

A project manager is conducting a risk workshop for a hybrid project. The team identifies 30 risks in 2 hours. The project manager wants to prioritize which risks deserve detailed response planning. What tool should be used next?

  1. A.Monte Carlo simulation — to quantify the cumulative probability impact of all 30 risks simultaneously and generate a probabilistic distribution of project schedule and cost outcomes.
  2. B.Failure Mode and Effects Analysis (FMEA) — to evaluate each risk's failure modes, severity, and likelihood in a structured format that prioritizes the most urgent responses.
  3. C.Probability-impact matrix — to quickly score each risk and focus detailed planning on high-priority risks
  4. D.Decision tree analysis — to evaluate the expected financial value of each response option and support informed trade-offs between different mitigation and contingency strategies.
Show answer and explanation

Correct answer: C

After risk identification, qualitative risk analysis using the probability-impact matrix is the first step to prioritize risks. Each risk is scored on probability and impact, placing it in low, medium, or high zones. High-priority risks receive detailed response planning; low-priority risks may be accepted with watch-list monitoring. This ensures effort is focused where it matters most. Monte Carlo and decision trees are quantitative tools used after qualitative prioritization. FMEA is used in manufacturing quality contexts.

Question 11 of 21

A risk response plan has been implemented for a key project risk. Which THREE activities are part of ongoing risk monitoring?

Select all that apply.

  1. A.Removing all risks from the register once their response plans are implemented
  2. B.Identifying new risks that emerge as the project environment changes
  3. C.Evaluating the effectiveness of implemented risk responses
  4. D.Tracking risk triggers to determine if a risk is about to materialize
  5. E.Reassessing the probability and impact of risks as the project progresses
Show answer and explanation

Correct answers: B and D and E

Ongoing risk monitoring includes: tracking risk triggers — early warning indicators that a risk is about to occur, enabling timely contingency plan activation; reassessing risk probability and impact — as the project advances, new information changes the risk profile; and identifying new risks — risk identification is continuous, not a one-time activity. Evaluating response effectiveness (E) is important but is more properly part of risk audits than routine monitoring. Risks should NOT be removed from the register simply because responses are implemented — they remain open until they are resolved, expired, or have occurred.

Question 12 of 21

The project team learns that a key supplier may not obtain permits before site work begins. What should happen FIRST?

  1. A.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  2. B.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  3. C.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: A

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 13 of 21

The project team learns that the probability of a data migration failure is rising as defects accumulate. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  3. C.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: B

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 14 of 21

The project team learns that a beneficial technology opportunity could reduce cycle time if adopted quickly. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  3. C.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: C

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 15 of 21

The project team learns that new legislation may affect one of the project's deliverables. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  3. C.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
  4. D.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
Show answer and explanation

Correct answer: D

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 16 of 21

The project team identifies an uncertainty that could either delay deployment or create a chance to simplify architecture. What should happen FIRST?

  1. A.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  2. B.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  3. C.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: A

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 17 of 21

The project team learns that an external dependency has become unstable after organizational restructuring. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  3. C.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: B

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 18 of 21

The project team learns that a previously low-priority risk is now affecting multiple work packages. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  3. C.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: C

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 19 of 21

The project team learns that risk owners have not updated their response actions for over a month. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  3. C.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
  4. D.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
Show answer and explanation

Correct answer: D

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 20 of 21

The project team learns that a threat was mitigated earlier, but the environment has now changed significantly. What should happen FIRST?

  1. A.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  2. B.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  3. C.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: A

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Question 21 of 21

The project team learns that a risk with an approved response plan is no longer aligned with the current project environment. What should happen FIRST?

  1. A.Wait for the risk to occur so the team can respond with complete information rather than investing in response plans for events that may never materialize.
  2. B.Update the risk analysis and response planning so owners, triggers, and actions reflect the current situation.
  3. C.Remove discussed risks from the register — once reviewed, retaining them adds administrative overhead without improving the team's ability to manage their most active risks.
  4. D.Escalate every risk to the steering committee regardless of severity — executive visibility ensures leadership can intervene proactively and is never caught off-guard by project challenges.
Show answer and explanation

Correct answer: B

Risk management is continuous. When conditions change, the project manager should reassess probability, impact, triggers, owners, and responses so decisions reflect current reality. Waiting, deleting risks prematurely, or escalating everything weakens the usefulness of the risk process.

Ready for exam conditions?

Practice these questions with randomized answer order and instant scoring, or take a full domain-weighted mock exam with a real exam timer.

More Process practice questions