Schedule Management PMP Practice Questions

Test yourself with 15 free, scenario-based PMP practice questions on schedule management, drawn from the Process domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Study first: PMP formulas cheat sheet

Question 1 of 15

Your project's critical path activity is running two weeks behind. The project deadline is fixed. Which schedule compression technique preserves the original scope while adding the LEAST risk?

  1. A.Fast tracking — overlap activities that were originally planned sequentially
  2. B.Crashing — add resources to the critical path activities
  3. C.Scope reduction — remove lower-priority deliverables
  4. D.Risk acceptance — inform the sponsor the deadline will be missed
Show answer and explanation

Correct answer: B

Crashing adds resources to critical path activities and generally introduces less risk than fast tracking because activities are not overlapped. Fast tracking increases rework and coordination risk by performing activities in parallel that were designed to be sequential. Scope reduction changes the project scope. Risk acceptance does not recover the schedule.

Question 2 of 15

A project manager needs to recover 10 days on a critical path activity. Crashing the activity costs $5,000 per day saved. Fast-tracking instead requires a dedicated integration resource for $30,000 but carries a 40% probability of 5 days of rework at $3,000/day. Which approach is MOST cost-effective if the full 10 days must be recovered?

  1. A.Fast-tracking: expected cost of $36,000 is less than crashing's $50,000
  2. B.Crashing: deterministic cost of $50,000 is preferable to fast-tracking's uncertain cost
  3. C.Fast-tracking: it is always cheaper than crashing on critical path activities
  4. D.Crashing: fast-tracking cannot recover a full 10 days
Show answer and explanation

Correct answer: A

Crashing cost = 10 days × $5,000 = $50,000 (certain). Fast-tracking cost = $30,000 (resource) + expected rework cost = 40% × 5 days × $3,000 = $6,000. Total expected fast-tracking cost = $30,000 + $6,000 = $36,000. The expected value analysis favors fast-tracking at $36,000 vs. $50,000 for crashing. However, if the risk averse sponsor prefers cost certainty, crashing may still be chosen. The question asks for the most cost-effective approach, so fast-tracking is the answer.

Question 3 of 15

On a hybrid project, a predictive design phase is 3 weeks behind. The agile delivery phase follows. Which technique should the project manager AVOID when trying to recover the design phase schedule?

  1. A.Crashing the design phase by adding subject matter experts
  2. B.Reducing the scope of the design deliverables without a formal change request
  3. C.Fast-tracking design activities that have low interdependency
  4. D.Starting agile delivery sprints before design is complete
Show answer and explanation

Correct answer: B

Reducing scope without a formal change request is scope creep in reverse — unauthorized scope reduction that bypasses integrated change control. All scope changes, including reductions, must follow the change management process. Crashing with SMEs and fast-tracking low-dependency activities are legitimate compression techniques. Starting early sprints represents a form of fast-tracking and may be acceptable with appropriate risk management.

Question 4 of 15

A project manager is crashing a project and has identified three critical path activities that can be crashed. Activity X: saves 2 days at $4,000/day. Activity Y: saves 3 days at $2,500/day. Activity Z: saves 1 day at $6,000/day. The project needs 4 days recovered. Which crashing sequence minimizes cost?

  1. A.Crash Activity X (2 days) then Activity Z (1 day) then Activity Y (1 day): total $16,500
  2. B.Crash Activity Y (3 days) then Activity Z (1 day): total $13,500
  3. C.Crash Activity Y (3 days) then Activity X (1 day): total $11,500
  4. D.Crash Activity X (2 days) then Activity Y (2 days): total $13,000
Show answer and explanation

Correct answer: C

Always crash the cheapest activity first. Rank by cost/day: Y ($2,500) → X ($4,000) → Z ($6,000). Crash Y for 3 days = 3 × $2,500 = $7,500. Need 1 more day — crash X for 1 day = $4,000. Total = $7,500 + $4,000 = $11,500. This is less than all other options. Any sequence that crashes Z pays $6,000/day unnecessarily, and starting with X gives up Y's cheaper days. Crashing must be applied sequentially to the cheapest option until the target is met.

Question 5 of 15

An agile release is behind by two sprints. The release date cannot move. The product owner proposes adding two developers to the team. The Scrum Master is concerned about this approach. What is the Scrum Master's concern based on?

  1. A.Adding developers increases technical debt — new team members write unfamiliar code that compounds existing complexity and slows the team further as they integrate into the codebase.
  2. B.Scrum teams must remain stable throughout the project — the Scrum stability principle requires consistent membership to maintain velocity predictability and reliable sprint commitments.
  3. C.New developers reset the velocity baseline — adding people requires a recalibration period before the team's story point commitments can be considered reliable again.
  4. D.Brooks's Law — adding people to a late project can make it later in the short term due to onboarding time, knowledge transfer.
Show answer and explanation

Correct answer: D

The Scrum Master's concern is based on Brooks's Law: 'Adding manpower to a late software project makes it later.' New developers require onboarding and knowledge transfer — consuming existing team members' time. Coordination overhead increases with team size (communication channels grow quadratically). Short-term productivity actually decreases before the new members become productive. The better alternatives may be: reduce scope (defer lower-priority stories), extend hours temporarily, or improve the team's process to increase velocity organically.

Question 6 of 15

On an office fit-out project, the electrical rough-in finished four days late. Drywall installation, the next activity on the critical path, can now only start four days after its planned date, and the forecast end date has moved by the same amount. What is the BEST next step?

  1. A.Submit a change request to move the schedule baseline end date by four days to reflect the late electrical rough-in work.
  2. B.Bring in a second drywall crew this week and ask the general contractor to absorb the extra cost within the current contract.
  3. C.Update the schedule with the actual finish, confirm the end-date impact, and compare recovery options for the downstream critical work.
  4. D.Ask the electrical subcontractor for a written explanation of the four-day delay and record it in the issue log as a supplier performance issue.
Show answer and explanation

Correct answer: C

The late predecessor has already pushed the forecast end date, so the project manager first needs an accurate picture: update the schedule with the actual finish, confirm the effect on the critical path, and compare recovery options such as crashing or fast tracking downstream work. Bringing in a second drywall crew may turn out to be a sensible fix, but committing to it before comparing options could spend money where a cheaper resequencing would work. Rebaselining through a change request accepts the slip before any recovery has been tried. Getting the subcontractor's explanation and logging the performance issue is reasonable, but it does nothing to protect the end date.

Question 7 of 15

A hybrid program shares one database specialist between a predictive infrastructure workstream and an agile application team. The infrastructure cutover milestone has zero float, and the specialist's sprint commitments keep pulling them away from cutover tasks. What should the project manager do FIRST?

  1. A.Review the specialist's assignments with the functional manager and product owner to agree priorities or find a qualified backup.
  2. B.Run resource leveling in the scheduling tool to remove the specialist's over-allocation, and accept the new cutover date it calculates.
  3. C.Escalate to the sponsor and request that the specialist be assigned exclusively to the cutover work until the milestone has been met.
  4. D.Ask the product owner to drop all of the specialist's stories from the next sprint and give the cutover milestone full priority.
Show answer and explanation

Correct answer: A

The delay comes from a resource conflict between two workstreams, and the milestone has no float to absorb it, so the project manager should bring the people who control the competing demands together. Reviewing the assignments with the functional manager and the product owner allows an informed decision on priorities or a substitute resource. Resource leveling with zero float simply moves the milestone, which accepts the delay rather than solving it. Escalating to the sponsor is premature while the conflict can still be resolved at the working level, and asking the product owner to drop stories decides the trade-off unilaterally without weighing the value of the application work.

Question 8 of 15

An agile team planned to run integration testing against a vendor's payment API in the next iteration. The vendor has just reported that the API will arrive three weeks late, which overlaps the planned testing window before the release. What is the BEST next step?

  1. A.Keep the iteration plan as it is and have the team run all of the integration tests in the final iteration once the vendor delivers.
  2. B.Ask the product owner to remove the payment testing stories and accept the release without integration testing against the vendor API.
  3. C.Contact the vendor's account manager to invoke the late-delivery penalty clause and ask for a recovery plan for the payment API.
  4. D.Work with the team and product owner to reorder the backlog and test against a stub of the vendor API until it arrives.
Show answer and explanation

Correct answer: D

In an agile setting, the team and product owner adapt the plan together when a dependency moves. Reordering the backlog and testing against a stub keeps the team delivering value and reduces the integration risk that remains once the real API arrives. Pushing all integration tests into the final iteration creates a big-bang test phase with no room to fix defects. Asking the product owner to drop the testing stories uses the right role for the wrong purpose and sacrifices quality. Invoking the penalty clause and requesting a vendor recovery plan may be appropriate through procurement, but it does not change the fact that the team's testing plan must be adapted now.

Question 9 of 15

On a predictive plant-upgrade project running two weeks behind, the team proposes starting construction of the foundations while the structural design is still about 60% complete. What should the project manager do NEXT?

  1. A.Approve the overlap at once and add the early foundation start to the risk register as an accepted risk owned by the site lead.
  2. B.Confirm which design and construction tasks can safely overlap and estimate the rework risk of starting the foundations early.
  3. C.Crash the remaining design activities by adding two structural engineers so the design is finished before any construction starts.
  4. D.Update the schedule network with the overlap, submit a change request to rebaseline, and notify the contractor of the new start date.
Show answer and explanation

Correct answer: B

Overlapping design and construction is fast tracking, which can recover time but increases the chance of rework if the design changes after foundations are poured. The project manager should confirm which dependencies are discretionary and estimate the rework exposure before the approach is adopted. Approving the overlap and logging it as an accepted risk records the risk without ever evaluating it. Crashing the design with extra engineers is a valid alternative, but choosing it now skips the comparison with fast tracking. Updating the network and submitting a change request to rebaseline formalizes the overlap before anyone has confirmed it is safe.

Question 10 of 15

On a hybrid project, the change control board approved a new regulatory reporting module requested by the compliance team because the regulator requires the new reports from go-live. The sponsor confirmed that the go-live date, which is tied to the regulator's deadline, must not move. What should the project manager do FIRST?

  1. A.Tell the team the board has approved the module and ask them to absorb it within the current iteration plan and budget.
  2. B.Review the approved change with the compliance team to find out whether the regulator would accept the module after go-live.
  3. C.Estimate the added work, update the schedule and backlog, and offer the sponsor options such as deferring lower-value features.
  4. D.Ask the product owner to place the reporting module at the top of the backlog and add iterations until the module is complete.
Show answer and explanation

Correct answer: C

Once a change is approved, the project manager integrates it into the plans and checks whether the fixed constraint can still be met. Estimating the added work, updating the schedule and backlog, and presenting options to the sponsor makes the trade-offs visible while the regulatory date is protected. Asking the team to absorb the work ignores the impact and puts the deadline at hidden risk. Reviewing with the compliance team whether the regulator would accept a later module reopens a need the board already approved because of that same regulator. Adding iterations until the module is done would move the go-live date the sponsor has said is fixed.

Question 11 of 15

A construction crew delivers site work in two-week iterations. Heavy rain over the last two iterations has cut the crew's completed outdoor work roughly in half, and the forecast shows more rain for the next month. What is the BEST next step?

  1. A.Reforecast with the team using the reduced velocity, and have the product owner pull indoor work forward so the crew stays productive.
  2. B.Keep forecasting from the original velocity and tell stakeholders the crew's average should recover once the rain stops.
  3. C.Review the weather records with the site supervisor to determine whether the lost days qualify as an excusable delay under the contract.
  4. D.Ask the product owner to remove the outdoor items from the release and keep the burnup chart on its planned line.
Show answer and explanation

Correct answer: A

Agile teams plan from actual performance, so the reduced velocity should be used to reforecast and the work should be adapted to conditions. Pulling indoor items forward keeps the crew productive while outdoor work is impractical, and the product owner keeps ownership of the ordering. Forecasting from the original velocity ignores evidence and hides the risk from stakeholders. Reviewing whether the lost days are an excusable delay may matter for the contract later, but it does not keep the crew productive or the forecast honest. Removing outdoor items to keep the burnup chart looking on track involves the product owner but manipulates the forecast instead of addressing the real constraint.

Question 12 of 15

A predictive medical device project needs the steering committee's design review gate before manufacturing can start. The review is two weeks past its planned duration. The project manager has learned that the reviewers are waiting for an updated biocompatibility test report, which the quality lead received a week ago but never forwarded. What should the project manager do NEXT?

  1. A.Start manufacturing setup at risk, record the assumption that approval will come, and brief the sponsor on the schedule exposure.
  2. B.Escalate to the sponsor and ask them to override the gate so the project can move into the manufacturing phase this week.
  3. C.Review the document control process with the quality manager to find out why the report was never forwarded to the reviewers.
  4. D.Have the quality lead send the biocompatibility report to the reviewers today and ask the committee chair for a decision date.
Show answer and explanation

Correct answer: D

The cause of the delay is already known: the reviewers lack a report the project already has. The fastest legitimate way to unblock the gate is to get that report to the reviewers immediately and secure a decision date. Starting manufacturing at risk, even with the assumption recorded and the sponsor briefed, bypasses a governance control and could waste effort if the design is not approved. Asking the sponsor to override the gate is unnecessary when the missing information can simply be supplied. Reviewing the document control process is a sensible follow-up to prevent a repeat, but it does not unblock the gate now.

Question 13 of 15

In a hybrid data center migration, three near-critical paths have lost most of their float over the past two reporting periods. The project manager's analysis shows that all three are waiting on the same shared test lab, which another project has booked for most of the next month. What should the project manager do NEXT?

  1. A.Wait until one of the near-critical activities becomes critical, and keep monitoring the three paths at the weekly schedule review.
  2. B.Negotiate with the other project manager and the lab owner to share the test lab slots so all three paths get lab time.
  3. C.Shift people from critical path activities to the near-critical ones so that their float stops shrinking any further.
  4. D.Analyze the three paths again with a Monte Carlo simulation to confirm the actual probability of missing the planned end date.
Show answer and explanation

Correct answer: B

The analysis has already identified the root cause, a shared test lab that another project has booked, so the next step is to resolve that constraint with the people who control it. Negotiating lab slots with the other project manager and the lab owner addresses the cause while the paths still have some float. Waiting until an activity becomes critical gives up the advantage of early detection. Running a Monte Carlo simulation repeats analysis that has already pointed to a clear cause and does not free up the lab. Moving people off the critical path does nothing about the lab conflict and could delay the end date directly.

Question 14 of 15

An agile team's integration work is three sprints behind the release plan. A senior manager offers four developers from another department and asks the project manager whether adding them will bring the integration work back on schedule. What is the BEST response?

  1. A.Accept the four developers right away and ask the team lead to pair each of them with an experienced developer starting tomorrow.
  2. B.Decline the four developers and ask the product owner to cut lower-value integration stories so the release date can hold.
  3. C.Ask the team where the four developers could help without onboarding slowing them, and report their view to the manager.
  4. D.Ask the product owner to keep the original integration date and plan the four new developers into the next sprint.
Show answer and explanation

Correct answer: C

Adding people to late work can help or hurt depending on onboarding effort, communication overhead and how divisible the remaining work is. The team knows best where new developers could contribute, so the project manager should ask them and give the manager an evidence-based answer. Accepting immediately and pairing everyone tomorrow commits experienced developers to onboarding before anyone knows whether it pays off. Declining and asking the product owner to cut stories rejects the help without checking where it could work, and scope trade-offs need a broader conversation. Asking the product owner to hold the date and plan the newcomers into the next sprint commits to an outcome before anyone has checked whether the extra developers will help.

Question 15 of 15

A predictive infrastructure project is six weeks behind. The project board asks the project manager for options to recover the schedule, but has stated that no deliverables may be removed from scope. What should the project manager do?

  1. A.Prepare crashing and fast tracking options for critical path activities so the board can compare cost, risk and time gained.
  2. B.Recommend removing the lowest-priority deliverables and present the six weeks of recovered time to the board as the fastest path.
  3. C.Crash every remaining activity so the board can see the maximum amount of time that the project could possibly recover.
  4. D.Fast track the remaining critical path activities immediately and inform the board of the revised dates at the next meeting.
Show answer and explanation

Correct answer: A

The board has asked for options within a fixed scope, so the project manager should develop schedule compression alternatives that target the critical path and show the cost, risk and time gained for each. This lets the board make an informed decision within its authority. Recommending scope removal ignores the constraint the board set. Crashing every remaining activity spends money on non-critical work that does not shorten the project. Fast tracking immediately may be one of the options, but implementing it before the board chooses bypasses the decision the board asked to make.