Question 1 of 7
During project execution, a key supplier delivers materials that fail quality inspection. Production cannot continue until replacement materials arrive, which will take 5 days. What should the project manager do FIRST?
- A.Log the issue in the issue log and wait for the supplier to resolve it independently — the supplier is contractually responsible for their delivery, and direct PM intervention may overstep contract boundaries.
- B.Issue a formal penalty notice per the contract's late delivery provisions — invoking penalty clauses signals the seriousness of the breach and triggers the contract's formal dispute resolution mechanism.
- C.Immediately escalate to the project sponsor — supplier delays of this severity require executive authority to compel the vendor to respond and protect the project schedule.
- D.Document the issue, assess the schedule impact, implement a workaround if possible (e.g., sequence other work to fill the gap).
Show answer and explanation
Correct answer: D
Effective issue management requires: (1) documenting the issue; (2) assessing the impact — 5 days could affect the schedule baseline; (3) implementing a workaround to minimize impact where possible; and (4) processing a change request if the baseline is affected. Simply waiting is passive. Penalty notices may be appropriate but do not solve the immediate production problem. Sponsor escalation is premature before the project manager has assessed the full situation and options.