Question 1 of 10
A project manager is dealing with a situation where requirements are still evolving and the buyer wants flexibility with some cost control. What should happen FIRST?
- A.Choose the fastest procurement option and negotiate details later — accelerating contract award reduces the schedule risk associated with delayed execution more than optimizing contract terms.
- B.Defer all significant decisions to the vendor — their domain expertise makes them better qualified to determine how to meet the project's technical requirements than the buying organization.
- C.Use the procurement strategy, contract type, and statement of work that best fit the risk, uncertainty, and performance incentives of the situation.
- D.Avoid documenting assumptions to preserve negotiation flexibility — explicit assumptions give vendors opportunities to price against them and reduce the buyer's room to maneuver.
Show answer and explanation
Correct answer: C
Procurement choices should be aligned to uncertainty, risk allocation, and desired incentives. The best first step is to match the sourcing and contract approach to the situation rather than optimizing only for speed or deferring key terms.