Test yourself with 19 free, scenario-based PMP practice questions on procurement and contract management, drawn from the Process domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Question 1 of 19

You are selecting a vendor for a complex software development engagement where requirements are not fully defined. Which contract type best protects the buyer while still incentivizing the vendor?

  1. A.Fixed-price lump sum contract
  2. B.Time-and-materials contract with a not-to-exceed ceiling
  3. C.Cost-plus-incentive-fee contract
  4. D.Cost-plus-fixed-fee contract
Show answer and explanation

Correct answer: C

A cost-plus-incentive-fee (CPIF) contract reimburses allowable costs and adds a fee that increases when performance targets are met — aligning vendor incentives with buyer outcomes. Fixed-price is risky when requirements are unclear, as vendors will price in uncertainty or fight scope changes. T&M with ceiling protects cost but provides no performance incentive. CPFF reimburses costs plus a fixed fee regardless of performance.

Question 2 of 19

A project manager is procuring a vendor for routine support services where the scope is clear and the price should be competitive. Which contract type is MOST appropriate?

  1. A.Cost-plus-fixed-fee (CPFF)
  2. B.Time-and-materials (T&M)
  3. C.Firm-fixed-price (FFP)
  4. D.Cost-plus-incentive-fee (CPIF)
Show answer and explanation

Correct answer: C

When scope is well-defined and work is routine, a Firm-Fixed-Price (FFP) contract is ideal. The buyer knows the exact cost upfront; the vendor assumes all cost risk and is incentivized to perform efficiently since they keep any savings. CPFF and CPIF are appropriate when scope is uncertain — they shift cost risk to the buyer. T&M is best for small, short-duration work where scope cannot be fully defined in advance. Well-defined scope + competitive market = FFP.

Question 3 of 19

A project manager receives a Request for Proposal (RFP) response from a vendor. The vendor's proposal price is 40% lower than the next lowest bidder. What should the project manager do?

  1. A.Award the contract now — the lowest price saves the project budget
  2. B.Disqualify the low bidder automatically for not meeting market rate standards
  3. C.Ask all vendors to rebid, using the low bid as the new benchmark
  4. D.Investigate the anomalously low bid for accuracy, completeness, and potential risk before making a decision
Show answer and explanation

Correct answer: D

An abnormally low bid is a red flag that warrants investigation. The vendor may have misunderstood the scope, made errors, planned to use substandard materials, or intends to recover costs through change orders. Awarding without scrutiny risks project failure if the vendor cannot deliver. Automatic disqualification may eliminate a legitimately efficient vendor. Asking all vendors to rebid is unethical and may violate procurement policy.

Question 4 of 19

The project team is preparing procurement documentation to solicit qualified vendors to compete for a complex professional services contract. Which document provides the detailed requirements against which vendors will prepare proposals?

  1. A.Request for Proposal (RFP)
  2. B.Request for Information (RFI)
  3. C.Request for Quotation (RFQ)
  4. D.Statement of Work (SOW)
Show answer and explanation

Correct answer: A

An RFP is used for complex professional services where the buyer wants the vendor to propose how they will meet the requirements — it solicits proposals including technical approach, qualifications, and price. RFI is used early to gather market information, not to solicit bids. RFQ is used when price is the primary selection criterion and scope is clearly defined. The SOW describes the work to be performed and is typically included within the RFP package, but is not itself the solicitation document.

Question 5 of 19

A project is using a time-and-materials contract for software consulting services. The project manager notices the vendor's billing hours have been increasing each month even though scope has not changed. What is the PRIMARY risk of T&M contracts that this illustrates?

  1. A.The vendor is incentivized to complete work quickly — T&M contracts create time pressure because the vendor's total revenue is constrained by the project's available budget ceiling.
  2. B.The buyer bears cost risk — there is no incentive for the vendor to control hours, as more hours mean more revenue.
  3. C.T&M contracts require competitive bidding each billing cycle — periodic re-bidding ensures the buyer continues to receive market-competitive rates for ongoing work throughout the project.
  4. D.The buyer cannot terminate a T&M contract without significant financial penalties — the open-ended structure creates contractual obligations that are costly and complex to exit early.
Show answer and explanation

Correct answer: B

The primary risk of T&M contracts is that they create a perverse incentive: the more hours the vendor bills, the more revenue they earn. This can lead to scope expansion, inefficiency, or billing padding. The buyer bears essentially unlimited cost risk unless a Not-to-Exceed (NTE) ceiling is added. This is why T&M contracts should be used only for short-duration work or when an NTE cap is in place. FFP and CPIF contracts better control this risk.

Question 6 of 19

A vendor is performing under a CPIF contract with a target cost of $500,000, target fee of $50,000, and a 70/30 sharing ratio (buyer/seller). The vendor completes the work for an actual cost of $440,000. What is the vendor's final fee?

  1. A.$50,000 — the fee is fixed regardless of performance
  2. B.$32,000 — the vendor shares in the savings but the buyer keeps the majority
  3. C.$68,000 — the vendor earns an additional fee for the $60,000 cost savings
  4. D.$80,000 — the vendor earns 30% of total costs as the fee
Show answer and explanation

Correct answer: C

Under a CPIF contract, cost savings are shared per the agreed ratio. Cost savings = Target Cost - Actual Cost = $500,000 - $440,000 = $60,000. Seller's share of savings = 30% × $60,000 = $18,000. Final fee = Target fee + Seller's share = $50,000 + $18,000 = $68,000. Total payment to vendor = AC + Final fee = $440,000 + $68,000 = $508,000. The buyer saves: $550,000 (target total) - $508,000 = $42,000, which is 70% of $60,000 = $42,000. The sharing ratio works correctly.

Question 7 of 19

During contract close-out on a construction project, the project manager must formally verify that the vendor completed all contractual obligations. What document provides the BEST basis for this verification?

  1. A.The final invoice submitted by the vendor
  2. B.The vendor's project manager's completion declaration
  3. C.The project risk register, showing all procurement risks as closed
  4. D.The original Statement of Work (SOW) and the procurement audit findings
Show answer and explanation

Correct answer: D

Contract closeout requires verifying that all contracted deliverables were completed per the SOW, which defines the agreed scope. A procurement audit conducted during closeout compares what was contracted against what was actually delivered. The vendor's invoice shows what they billed but not whether deliverables were accepted. The vendor's own declaration is not independent. The risk register tracks risks, not contractual obligations.

Question 8 of 19

A project manager needs to procure specialized equipment but has only three approved vendors in the organization's vendor list, and none have delivered this equipment type before. What should the project manager do?

  1. A.Select the vendor with the lowest price from the approved list — minimizing cost on pre-qualified vendors is the safest procurement approach, and all three have already passed organizational qualification standards.
  2. B.Issue a Request for Information (RFI) to all three vendors and potentially qualify new vendors through the organization's vendor qualification process.
  3. C.Manufacture the equipment internally to avoid procurement risk — if the existing vendor list cannot meet requirements, bringing production in-house eliminates all external supply chain uncertainty.
  4. D.Award the contract to any vendor on the current approved list and accept the capability mismatch — working with a qualified-but-imperfect vendor is preferable to the delay of opening new procurement channels.
Show answer and explanation

Correct answer: B

When existing vendors lack the required capability, the project manager should first gather market information via an RFI to understand vendor capabilities, then work through the organization's vendor qualification process to add capable vendors if needed. An RFI is a market intelligence tool — not a solicitation for bids — that helps assess supplier landscape before committing to a procurement approach. Awarding to an unqualified vendor risks performance failure. Internal manufacturing is a make-or-buy decision requiring formal analysis.

Question 9 of 19

A hybrid project needs an external vendor to build a customer portal whose detailed requirements will emerge over several iterations. The sponsor wants room to adjust features as feedback arrives but insists on a firm limit on total spend. The procurement manager asks the project manager which contract approach to recommend. What should the project manager recommend?

  1. A.Recommend a firm fixed price contract that locks in the sponsor's spending limit, with every current portal feature listed in the statement of work.
  2. B.Recommend time and materials with a not-to-exceed ceiling, with the statement of work describing iteration goals rather than every feature.
  3. C.Recommend a cost plus percentage of cost contract that lets the vendor absorb evolving portal requirements without repeated price renegotiation.
  4. D.Delay the procurement until the product owner has finalized every portal requirement and the vendor can quote a single fixed price.
Show answer and explanation

Correct answer: B

The requirements will keep evolving, yet the sponsor needs a hard spending limit, so time and materials with a not-to-exceed ceiling gives flexibility while capping the buyer's exposure. Framing the statement of work around iteration goals fits the hybrid approach. A firm fixed price with today's features listed in the statement of work looks like cost control but will generate frequent change orders and disputes as the scope shifts. A cost plus percentage of cost contract rewards the vendor for spending more and offers no ceiling. Waiting until every requirement is final defeats the purpose of iterative delivery and delays the portal.

Question 10 of 19

An agile team needs an external firm to migrate 40 legacy reports to a new analytics platform. Each report is fully specified, the specifications have been stable for months, and finance requires price certainty before approving the purchase. What should the project manager propose?

  1. A.Use a time and materials agreement billed per sprint, keeping the vendor contract flexible in line with the team's agile way of working.
  2. B.Offer a cost plus incentive fee contract that rewards the firm for finishing the report migration below the target cost estimate.
  3. C.Propose a firm fixed price for the 40 documented reports, with acceptance criteria for each report written into the statement of work.
  4. D.Let the firm start under a letter of intent, then add the acceptance criteria and final price to the statement of work after the first sprint.
Show answer and explanation

Correct answer: C

When scope is well defined and stable and the buyer needs price certainty, a firm fixed price contract is the best fit, even inside an agile project. Clear acceptance criteria per report make delivery verifiable. Time and materials gives up the price certainty finance requires simply because the team works in sprints. A cost plus incentive fee contract still leaves the final cost open and suits uncertain work, not a stable migration. Starting under a letter of intent and settling the statement of work and price later exposes the buyer to cost risk before anything is agreed.

Question 11 of 19

A predictive project is contracting a construction firm to build an electrical substation. The scope and design are complete. The sponsor wants the firm to finish before the winter demand peak and to pass the utility's inspections on the first attempt, and is willing to pay more for both outcomes. What should the project manager recommend?

  1. A.Use a fixed price incentive fee contract, with the bonus tied to measurable early completion dates and first-time inspection pass rates.
  2. B.Use a firm fixed price contract with the full design in the statement of work, and pay a discretionary bonus at closing if the team is satisfied.
  3. C.Use a cost plus fixed fee contract that lets the construction firm add crews whenever they are needed to reach the winter completion date.
  4. D.Add liquidated damages for late delivery to a firm fixed price contract, so the construction firm is pressed to finish before the winter peak.
Show answer and explanation

Correct answer: A

The design is complete, so a fixed price base is appropriate, and the sponsor wants to reward specific outcomes, which calls for a fixed price incentive fee with objective, measurable targets for early completion and inspection results. A discretionary bonus at closing is subjective and not enforceable, so it does little to motivate the firm. A cost plus fixed fee contract shifts cost risk to the buyer and gives the firm no incentive to finish early or meet quality targets. Liquidated damages penalize lateness but do not reward early delivery or quality, so they only address part of what the sponsor wants.

Question 12 of 19

A hybrid program needs two cybersecurity consultants for about six weeks to review the architecture of a new release. Nobody can yet say how many hours the review will take, and the consultants must start before the next release planning session. What contract approach should the project manager use?

  1. A.Request a firm fixed price from the consultants for the whole review, using the current architecture documents as the basis for their quote.
  2. B.Issue a cost plus award fee contract with a panel that scores the consultants' work at the end of the six-week review.
  3. C.Have human resources recruit two permanent security engineers who can stay on the program while the review effort is still unknown.
  4. D.Use time and materials with agreed hourly rates and a not-to-exceed amount, reviewing hours used at each iteration.
Show answer and explanation

Correct answer: D

Short, specialized staff augmentation with uncertain effort is the classic case for time and materials, and a not-to-exceed amount with regular reviews of hours keeps cost under control. It also lets the consultants start quickly. A firm fixed price would force the consultants to price in the unknown effort or lead to disputes over what the review includes. A cost plus award fee contract adds administrative overhead that is out of proportion for a six-week engagement. Recruiting permanent staff is slow and does not match a short, temporary need.

Question 13 of 19

An agile product team wants a university lab to explore whether a new machine learning technique can detect fraud in real time. The lab estimates the research could take up to two years, and nobody knows whether the technique will work at all. How should the project manager structure the agreement with the lab?

  1. A.Negotiate a firm fixed price with the lab for a working fraud detection algorithm, so the cost of failed experiments shifts to the lab.
  2. B.Fund the lab's costs in short increments, with a review of findings and a go/no-go decision by the product owner after each one.
  3. C.Write a statement of work listing every experiment the lab must run and track research progress against those planned tasks.
  4. D.Sign one cost-reimbursable contract for the full two years and have the product owner review the findings at the final demonstration.
Show answer and explanation

Correct answer: B

Research with uncertain outcomes suits a cost-reimbursable arrangement, and in an agile setting it should be funded in short increments so the product owner can inspect findings and stop or continue based on evidence. This limits the buyer's exposure if the technique proves unworkable. A firm fixed price for a working algorithm would be refused or heavily padded because the lab cannot control whether the technique succeeds. A detailed list of experiments assumes knowledge nobody has yet and removes the flexibility research needs. A single two-year cost-reimbursable contract uses the right contract type but delays any learning or decision point until the money is spent.

Question 14 of 19

Three months into a predictive project, a vendor has missed two contractual delivery dates for test equipment. The vendor claims the statement of work only requires delivery to the loading dock, not installation, while the buyer's team reads it as delivery and installation. What should the project manager do FIRST?

  1. A.Review the disputed statement of work clauses, document the missed dates, and raise them with the vendor through the contract's claims process.
  2. B.Withhold all remaining payments to the vendor until they accept the buyer's reading of the statement of work and make up for both missed delivery dates.
  3. C.Refer the disagreement straight to arbitration, since the vendor's reading of the statement of work differs from the buyer's.
  4. D.Issue the vendor a notice of termination for default citing the two missed delivery dates for the test equipment.
Show answer and explanation

Correct answer: A

Contested changes and disputed interpretations are handled through the contract's claims administration process, starting with a clear review of the actual terms and documented evidence of performance. Negotiating on that basis is the preferred first path to resolution. Withholding all payments without contractual grounds may itself breach the contract and escalate the conflict. Arbitration is an alternative dispute resolution step used when negotiation fails, not the first move. Terminating for default is premature while the scope interpretation is still disputed and may expose the buyer to a wrongful termination claim.

Question 15 of 19

A hybrid project needs specialized lidar sensors for an autonomous vehicle prototype. Only three suppliers worldwide can produce them, and industry reports suggest all three have long and growing lead times, but none has confirmed its current capacity or commercial terms. The project's integration sprint depends on receiving the sensors in five months. What should the project manager do FIRST?

  1. A.Award the contract to the supplier with the lowest catalog price right away, before other buyers in the market take the limited capacity.
  2. B.Issue a fixed price request for proposal to the three qualified suppliers right away, with delivery within five months as a mandatory requirement.
  3. C.Have the engineering team re-evaluate the prototype design for alternative sensor types before any of the three suppliers is contacted.
  4. D.Issue a request for information to the three qualified suppliers to confirm capacity, lead times and terms before choosing a strategy.
Show answer and explanation

Correct answer: D

With a constrained market, the project manager first needs reliable information about the three suppliers' actual capacity, lead times and terms, which a request for information provides. That evidence then shapes the procurement strategy and the response to the schedule risk. Awarding to the lowest catalog price skips evaluation and may lock the project into a supplier that cannot deliver in five months. Issuing a fixed price request for proposal right away targets the right suppliers but jumps to solicitation before the project knows whether any of them can deliver in time or which contract type and strategy fit the market. Having engineering re-evaluate the prototype for alternative sensors studies the wrong question first: the design may not need to change, and the delay in contacting the only qualified suppliers eats into the five-month window.

Question 16 of 19

An agile team building a mobile banking app must decide whether to develop its own payment module or integrate a third-party payment component. The team has strong developers but little experience with payment card security standards, and the release is planned in four months. What should the project manager do FIRST?

  1. A.Let the developers build the payment module in house, since agile teams own the solution and outsourcing would slow their delivery cadence.
  2. B.Ask the product owner to pick a payment vendor from an online search and add the component to the backlog for the next sprint.
  3. C.Run a make-or-buy analysis with the team and product owner, comparing cost, skills, compliance needs and delivery time for each option.
  4. D.Have the developers assess the cost and effort of building the payment module in house, then decide based on that estimate.
Show answer and explanation

Correct answer: C

A make-or-buy analysis is the first step before any procurement decision, and here it must weigh the team's limited experience with payment security standards against cost and the four-month release. Involving the team and product owner keeps the decision collaborative and tied to product value. Building in house by default ignores the compliance gap. Having the product owner pick a vendor from a web search skips evaluation of the options. Having the developers assess only the in-house build cost and effort is too narrow, because it leaves out the payment security compliance gap and never compares buying the component.

Question 17 of 19

Engineering recommends buying a single vendor's control platform for a critical plant upgrade on a predictive project. A market review that engineering completed last month confirmed that no other product is compatible with the plant's existing systems. The organization's procurement policy normally requires at least three competitive bids. What should the project manager do NEXT?

  1. A.Sign the contract with the platform vendor now, since there is no real competition and a longer process would only delay the plant upgrade.
  2. B.Prepare a sole-source justification under the procurement policy that cites engineering's market review, and route it for approval.
  3. C.Run a full competitive bid with three suppliers anyway, even though engineering's market review found only one compatible platform.
  4. D.Let the platform vendor draft the statement of work and contract terms, given its deeper knowledge of the control platform.
Show answer and explanation

Correct answer: B

Sole-source procurement is allowed, but it must follow the organization's policy, and engineering's market review has already settled that no alternative fits, so the next step is to document that evidence in a sole-source justification and obtain approval for the exception. That protects the organization and gives a basis for negotiating terms with a vendor that faces no competition. Signing right away bypasses the procurement policy. Running a full bid after the review found only one compatible product wastes time and may not be what the policy requires once an exception is justified. Letting the vendor write the statement of work and terms hands control of the agreement to the party with the most to gain.

Question 18 of 19

On a hybrid project, the client asks for a new regulatory reporting format in a deliverable defined in a fixed price contract with an external vendor. The vendor estimates the change adds about two weeks of work and extra cost. After reviewing the estimate with the team, the project manager agrees the change is needed. What should the project manager do NEXT?

  1. A.Submit a change request through the contract change control process, so the impact is assessed and, if approved, the contract is amended.
  2. B.Tell the vendor to start the new reporting format now, and record the change in the contract at the next monthly vendor review meeting.
  3. C.Insist that the vendor absorb the extra two weeks of work within the fixed price already agreed for the deliverable in the contract.
  4. D.Have the procurement manager sign a contract amendment today, then submit the change request afterward so the project change log stays complete.
Show answer and explanation

Correct answer: A

Changes to contracted deliverables must go through the contract change control process so their schedule and cost impact is evaluated and approved before the contract is formally amended. Only then should the vendor do the new work. Directing the vendor to start before approval creates a constructive change and a likely claim. Insisting the vendor absorb new work that was not in the original scope is unfair and invites a dispute. Signing the amendment before the change request uses the right documents in the wrong order and skips the impact assessment.

Question 19 of 19

Before launching a major procurement, the project manager is asked whether the organization should build internally, outsource, or pursue a blended approach. What process should come FIRST?

  1. A.Issue the RFP immediately to start receiving market responses — early engagement surfaces viable vendor options and drives the sourcing decision forward without further internal analysis.
  2. B.Plan the sourcing strategy by evaluating needs, constraints, capabilities, and risk before selecting the procurement path.
  3. C.Request a proposal from the lowest-cost vendor as the first step — a market price signal provides a practical foundation for procurement planning without extensive internal analysis.
  4. D.Delay the sourcing decision until execution when more scope context is available — early procurement commitments made under uncertainty create contractual risk that is better avoided.
Show answer and explanation

Correct answer: B

Sourcing strategy should be planned before approaching the market. The organization needs clarity on needs, constraints, risk, and internal capability before deciding how to source.