Question 1 of 7
Halfway through a predictive project, a stakeholder requests a significant new feature not included in the project charter. The feature would add three weeks to the schedule. What should you do FIRST?
- A.Submit the request through the integrated change control process for evaluation
- B.Add the feature now to keep the stakeholder satisfied
- C.Reject the request because the scope was already agreed upon
- D.Add the feature and compress the remaining schedule to absorb the impact
Show answer and explanation
Correct answer: A
All scope changes on a predictive project must go through integrated change control. This ensures the impact on schedule, cost, risk, and quality is formally evaluated before a decision is made. Adding without process (A, D) is scope creep. Outright rejection ignores the stakeholder's legitimate request and bypasses the proper process.