Question 1 of 10
During performance review, the project manager notes that EV is lower than AC. What does this MOST likely indicate?
- A.The project is over budget for the work accomplished
- B.The project must be performing well because spending is occurring as work is being done
- C.No conclusion can be drawn because earned value data is not useful for project decisions
- D.The only correct response is to request more budget now
Show answer and explanation
Correct answer: A
Earned value analysis helps interpret cost and schedule performance in context. The right conclusion depends on how planned, earned, and actual values relate to one another. Looking at spend alone or jumping directly to budget requests bypasses the insight that performance metrics are intended to provide.