Question 1 of 7
A project manager is asked to provide a rough order-of-magnitude (ROM) estimate for a new project with very limited information. Which estimating technique is MOST appropriate?
- A.Analogous estimating — use actual cost data from a similar past project as the basis
- B.Bottom-up estimating — estimate each work package and roll up to a total
- C.Three-point estimating — develop optimistic, pessimistic, and most likely estimates
- D.Parametric estimating — use a statistical model based on project parameters
Show answer and explanation
Correct answer: A
When project information is limited (early in initiation), analogous estimating uses historical data from similar completed projects to produce a high-level estimate quickly. ROM estimates typically range from -25% to +75% accuracy. Bottom-up requires detailed WBS decomposition — not possible with limited information. Three-point and parametric estimating require more project detail and validated parameters. Analogous estimating is fast, cheap, and appropriate for early-stage estimates.