Question 1 of 5
A Kanban team's WIP limit for the 'In Progress' column is 4. Currently there are 4 items in progress and a developer finishes one item, moving it to 'Done'. Another developer wants to pull a new item from 'To Do'. What should happen?
- A.The developer must wait — pulling now would bring the column WIP to 4, which equals the stated limit and violates the Kanban constraint that governs this column.
- B.The WIP limit applies to the full board, not individual columns — a single-column count of 4 is only a constraint if it causes the total board WIP limit to be breached.
- C.The developer should request manager permission before exceeding the WIP limit — changing capacity constraints requires authorization from whoever governs the team's Kanban system.
- D.The developer can pull the new item since finishing one item brought the WIP to 3, which is below the limit
Show answer and explanation
Correct answer: D
After one item moves to 'Done', the 'In Progress' column has 3 items — below the WIP limit of 4. The developer can pull a new item from 'To Do'. The WIP limit prevents overloading the column to more than 4 at any one time. WIP limits create a pull system: work is pulled only when capacity exists, preventing bottlenecks and ensuring flow. No manager approval is needed — the WIP limit itself is the governing rule.