Question 1 of 6
You are negotiating with a department head to obtain a key resource for your project. The department head is concerned about the impact on their team's own deliverables. You know the resource is only needed for six weeks. What negotiation technique is MOST likely to result in agreement?
- A.Emphasize the strategic importance of your project to help the department head understand their organizational obligation to contribute resources to high-priority cross-departmental initiatives.
- B.Ask the project sponsor to mandate the resource transfer — executive sponsorship provides the formal authority needed to direct functional departments to contribute to high-priority projects.
- C.Offer a reciprocal resource-sharing arrangement — proposing to lend your own team members in exchange creates a fair trade that the department head is more likely to accept.
- D.Focus on the department head's interest — protecting their team's deliverables — and propose a time-boxed arrangement with a clear return date that minimizes disruption.
Show answer and explanation
Correct answer: D
Interest-based negotiation focuses on the other party's underlying needs, not their stated position. By addressing the department head's real concern — protecting their team's deliverables — with a clear time-boxed arrangement, you reduce their perceived risk and make agreement easier. Emphasizing strategic importance creates pressure rather than mutual benefit. Sponsor mandate bypasses negotiation and damages the relationship. A reciprocal offer may work but is not necessarily the MOST effective technique here — understanding the interest directly is more targeted.