Question 1 of 18
Two functional managers are competing for the same specialized resource on your project. Both claim the resource is critical to their work stream. The resource cannot be shared simultaneously. What is the BEST approach to resolve this conflict?
- A.Facilitate a problem-solving session with both managers, using project priorities and schedule impacts to objectively evaluate how the resource should be sequenced.
- B.Let the two functional managers resolve the resource conflict between themselves — as PM you lack formal authority over either functional department, and escalating above them would damage those working relationships.
- C.Escalate to the project sponsor and ask them to decide which workstream takes priority — executive-level resource conflicts require a decision from someone with authority over both competing departments.
- D.Split the resource's time equally between both workstreams to prevent either manager from feeling their project is deprioritized, maintaining stakeholder relationships at the cost of some efficiency.
Show answer and explanation
Correct answer: A
The confronting/problem-solving approach is the most effective conflict resolution technique. Using objective criteria — project priorities and schedule impact — depersonalizes the conflict and leads to sustainable decisions. Leaving it to them risks an unresolved standoff. Escalating immediately skips the PM's responsibility to resolve conflicts at the lowest appropriate level. Equal time-splitting may sub-optimize both workstreams and doesn't address actual priority.