Question 1 of 11
An agile team member tells you they are struggling to understand the acceptance criteria for a user story. The sprint ends in two days. What should a servant leader project manager do FIRST?
- A.Rewrite the acceptance criteria yourself and distribute them to the team
- B.Connect the team member with the product owner to clarify requirements together
- C.Move the story to the next sprint to allow more preparation time
- D.Tell the team member to do their best and raise any questions at the retrospective
Show answer and explanation
Correct answer: B
A servant leader removes impediments and facilitates connections. Connecting the developer with the product owner addresses the root cause — unclear requirements — while empowering both parties. Rewriting requirements yourself undermines team ownership. Moving the story may not be necessary. Deferring to the retrospective is too late.