Question 1 of 19
You are a project manager leading a cross-functional agile team. Two senior developers have an ongoing conflict that is slowing down sprint velocity. What is the BEST first step to address this situation?
- A.Facilitate a private conversation with both developers to understand each person's perspective and work toward a workable resolution.
- B.Escalate the conflict to the project sponsor, ensuring executive visibility and access to the authority needed to enforce a resolution between the two senior developers.
- C.Reassign one of the developers to a different project to eliminate the source of conflict, preventing further sprint velocity loss caused by the ongoing interpersonal dynamic.
- D.Ignore the conflict and allow the team to self-organize a resolution — agile principles favor team autonomy, and self-directed teams often resolve interpersonal issues more effectively without management involvement.
Show answer and explanation
Correct answer: A
The best first step is to facilitate a direct, private conversation (confronting/problem-solving). This allows both parties to express their perspectives and work toward resolution. Escalation should come only after direct resolution attempts fail. Reassignment avoids the root cause. Ignoring allows the conflict to fester and worsen velocity further.