Question 1 of 6
Your project has stakeholders in different roles: an executive sponsor who prefers concise dashboards, subject-matter experts who need technical detail, and end users who need plain-language guidance. What communication approach BEST serves all groups?
- A.Create one comprehensive status report and distribute it to all stakeholders — a single unified report ensures everyone has the same information and prevents conflicting narratives across different audience groups.
- B.Hold weekly all-hands meetings to ensure everyone receives the same information simultaneously, eliminating the risk of key stakeholders learning about developments through informal channels.
- C.Let each stakeholder group request information on an ad hoc basis — this reduces communication overhead and ensures only interested parties receive updates, avoiding information overload.
- D.Tailor the content, format, and frequency of communications to the specific needs and preferences of each stakeholder group.
Show answer and explanation
Correct answer: D
Effective communication is tailored — the right message, in the right format, through the right channel, to the right audience. A single report will either be too dense for executives or too shallow for SMEs. All-hands meetings are inefficient for information that varies by role. Ad hoc requests create information gaps and reactive management.