Question 1 of 17
A vendor is requesting a 20% price increase mid-project, citing material cost inflation. This increase exceeds your project budget. What is the BEST negotiation approach?
- A.Reject the increase outright — the vendor accepted the cost risk at contract signing and is contractually bound to deliver at the agreed price regardless of market changes.
- B.Accept the full increase to maintain the vendor relationship and avoid the schedule risk of sourcing a replacement supplier at this stage of the project.
- C.Escalate to the project sponsor since budget deviations of this magnitude require their authorization and senior-level involvement in the negotiation.
- D.Explore options such as phased increases, scope reductions, or longer payment terms to reach a workable solution.
Show answer and explanation
Correct answer: D
Principled (interest-based) negotiation seeks mutual gain. Exploring creative options — partial increases, adjusted scope, payment flexibility — is more likely to preserve the relationship and reach agreement than positional approaches. Outright rejection risks losing the vendor. Full acceptance blows the budget. Escalating immediately avoids your responsibility as project manager.