Negotiation and Influence PMP Practice Questions

Test yourself with 17 free, scenario-based PMP practice questions on negotiation and influence, drawn from the People domain of the exam and aligned to PMBOK 8. Work through each scenario before revealing the answer — every question includes an explanation of why the correct choice is right. For randomized, interactive practice across all topics, use the practice question tool.

Study first: how to answer PMP situational questions

Question 1 of 17

A vendor is requesting a 20% price increase mid-project, citing material cost inflation. This increase exceeds your project budget. What is the BEST negotiation approach?

  1. A.Reject the increase outright — the vendor accepted the cost risk at contract signing and is contractually bound to deliver at the agreed price regardless of market changes.
  2. B.Accept the full increase to maintain the vendor relationship and avoid the schedule risk of sourcing a replacement supplier at this stage of the project.
  3. C.Escalate to the project sponsor since budget deviations of this magnitude require their authorization and senior-level involvement in the negotiation.
  4. D.Explore options such as phased increases, scope reductions, or longer payment terms to reach a workable solution.
Show answer and explanation

Correct answer: D

Principled (interest-based) negotiation seeks mutual gain. Exploring creative options — partial increases, adjusted scope, payment flexibility — is more likely to preserve the relationship and reach agreement than positional approaches. Outright rejection risks losing the vendor. Full acceptance blows the budget. Escalating immediately avoids your responsibility as project manager.

Question 2 of 17

You are negotiating with a department head to obtain a key resource for your project. The department head is concerned about the impact on their team's own deliverables. You know the resource is only needed for six weeks. What negotiation technique is MOST likely to result in agreement?

  1. A.Emphasize the strategic importance of your project to help the department head understand their organizational obligation to contribute resources to high-priority cross-departmental initiatives.
  2. B.Ask the project sponsor to mandate the resource transfer — executive sponsorship provides the formal authority needed to direct functional departments to contribute to high-priority projects.
  3. C.Offer a reciprocal resource-sharing arrangement — proposing to lend your own team members in exchange creates a fair trade that the department head is more likely to accept.
  4. D.Focus on the department head's interest — protecting their team's deliverables — and propose a time-boxed arrangement with a clear return date that minimizes disruption.
Show answer and explanation

Correct answer: D

Interest-based negotiation focuses on the other party's underlying needs, not their stated position. By addressing the department head's real concern — protecting their team's deliverables — with a clear time-boxed arrangement, you reduce their perceived risk and make agreement easier. Emphasizing strategic importance creates pressure rather than mutual benefit. Sponsor mandate bypasses negotiation and damages the relationship. A reciprocal offer may work but is not necessarily the MOST effective technique here — understanding the interest directly is more targeted.

Question 3 of 17

You are negotiating a contract amendment with a supplier. The supplier's representative becomes increasingly aggressive, using high-pressure tactics and ultimatums. What is the BEST negotiation response?

  1. A.Match the stakeholder's aggressive posture to signal that you will not be intimidated — negotiators who respond passively to pressure tactics invite further exploitation and weaken their position.
  2. B.Accept their terms to end the unpleasant interaction and preserve the working relationship — a damaged relationship from a contested negotiation has longer-term project costs than any single concession.
  3. C.Call out the tactic calmly and without accusation, then redirect the conversation to interests and objective criteria.
  4. D.Walk away from the negotiation and escalate to a senior leader — some negotiations are not productive to continue, and removing yourself signals that unacceptable tactics will not achieve results.
Show answer and explanation

Correct answer: C

When a counterpart uses pressure tactics, principled negotiators name the tactic neutrally (e.g., 'It seems we have a firm deadline — can you help me understand what is driving that?') and redirect to interests and objective criteria. Matching aggression escalates the conflict. Capitulating rewards pressure tactics and produces a bad outcome. Walking away may be appropriate as a last resort but not as a first response.

Question 4 of 17

The product owner wants to add three high-priority features to the current sprint that is already fully committed. The development team says the current scope is at capacity. As the scrum master, how should you facilitate this negotiation?

  1. A.Tell the product owner that sprint scope is locked once planning is complete — protecting sprint commitments is a core Scrum practice and the product owner must respect the team's agreed capacity.
  2. B.Allow the features to be added and ask the team to work extended hours — the product owner's high-priority requests represent business value that justifies temporary overextension of the team.
  3. C.Split the sprint into two parallel mini-sprints — dividing work into separate tracks preserves the original commitments while also creating capacity for the new high-priority items.
  4. D.Facilitate a conversation where the product owner and team jointly evaluate the value and effort of both existing and new items.
Show answer and explanation

Correct answer: D

The scrum master's role is to facilitate, not to impose rules or solutions. A joint conversation where the product owner and team evaluate priorities transparently respects both the PO's value decisions and the team's capacity. Simply blocking the PO is rigid and doesn't help them make an informed trade-off. Mandating overtime burns out the team and ignores sustainable pace principles. Splitting the sprint disrupts the rhythm and creates confusion about goals.

Question 5 of 17

You are negotiating final acceptance criteria with a client who keeps expanding the scope of 'done' at each review. Your team has delivered exactly what was specified but the client keeps finding new requirements. What is the BEST negotiation strategy?

  1. A.Use the original signed requirements document as objective criteria, differentiate between agreed scope and new requests.
  2. B.Agree to each new requirement to maintain client satisfaction — accommodating client requests builds goodwill and avoids contract disputes that would cost more in time and relationship damage than the additions.
  3. C.Refuse to make any changes since the original specification was formally agreed upon — honoring the documented contract scope is both legally and professionally correct.
  4. D.Escalate to legal to enforce the original contract terms — unauthorized scope expansion is a contractual matter that requires legal review before any response is given to the client.
Show answer and explanation

Correct answer: A

Principled negotiation uses objective criteria — in this case, the signed requirements document — to anchor discussions and separate agreed scope from new requests. This is firm but fair and keeps the relationship intact. Agreeing to all new requirements rewards scope creep and impacts cost and schedule. Refusing all changes ignores potentially legitimate client needs. Legal escalation is disproportionate and damages the relationship.

Question 6 of 17

You are entering a negotiation with an internal stakeholder over resource allocation. Before the meeting, what is the MOST important preparation step based on principled negotiation principles?

  1. A.Prepare a list of your maximum demands and open with an ambitious position — anchoring high creates room for concessions and signals confidence that shapes the negotiation from the start.
  2. B.Research counterarguments to all of the stakeholder's expected objections — being prepared to refute resistance positions you as a credible, well-prepared negotiator from the first exchange.
  3. C.Ask your project sponsor to attend the negotiation — having executive presence in the room adds organizational weight to your position and signals that your requests have leadership backing.
  4. D.Identify your BATNA (Best Alternative to a Negotiated Agreement) and understand the stakeholder's likely interests and concerns.
Show answer and explanation

Correct answer: D

Principled negotiation preparation focuses on understanding interests (not just positions) and knowing your BATNA — the alternative if the negotiation fails. Your BATNA defines your walk-away point and gives you realistic confidence. Preparing extreme opening demands is positional bargaining, which is less effective. Preparing only counter-arguments is adversarial and ignores the stakeholder's legitimate interests. Sponsor pressure can damage relationships and skips the negotiation step.

Question 7 of 17

During sprint planning, the product owner insists on including a low-effort, high-value feature in the sprint. The team estimates it at 13 story points but the sprint capacity is already at 40 of 40 points. After negotiation, the PO suggests removing a 13-point story to make room. The team disagrees, saying that story is technically critical. What negotiation principle applies, and what should happen?

  1. A.The product owner has final authority over the backlog — their story selection should override the team's technical objections, since value delivery is the product owner's primary responsibility.
  2. B.The team has final authority over what fits in a sprint — the product owner must accept the team's decision, since sustainable pace and technical integrity are the team's accountability to protect.
  3. C.Both value and technical necessity are legitimate criteria — the team and PO should jointly evaluate all stories using both criteria and make an informed trade-off decision together.
  4. D.Add the feature to the sprint and accept a velocity overcommitment for this iteration — delivering the business-critical feature now is more important than maintaining a perfectly sized sprint.
Show answer and explanation

Correct answer: C

Principled negotiation uses objective, shared criteria. Both business value (the PO's criterion) and technical necessity (the team's criterion) are legitimate considerations in sprint planning. The decision should be made jointly, transparently, and with full information. Neither party has unilateral authority that overrides legitimate concerns. The PO owns prioritization of business value, but the team owns capacity and technical decisions — these must be reconciled collaboratively. Overcommitting violates sustainable pace.

Question 8 of 17

Two predictive projects need the same specialized architect during the same month. After comparing both schedules with the other project manager, you find your project needs the architect only for design reviews in weeks 1 and 3, while the other project needs hands-on support in weeks 2 and 4. What is the BEST next step?

  1. A.Propose to the other project manager that the architect do this project's reviews in weeks 1 and 3 and the other project's build in weeks 2 and 4
  2. B.Ask the resource manager to assign the architect for the full month to whichever project has the higher priority score in the portfolio ranking
  3. C.Request approval from the sponsor to bring in a contract architect for the design reviews and leave the internal architect with the other project
  4. D.Meet again with the other project manager to review both schedules for float and look for a way to move one project's architecture work into next month
Show answer and explanation

Correct answer: A

The schedule comparison already shows the two needs fit together, so the best step is to propose the week-by-week split to the other project manager, who shares the same interest in getting the architect when needed. Asking the resource manager to choose by portfolio ranking turns a solvable conflict into a win-lose decision and ignores the analysis just completed. Hiring a contract architect adds cost and onboarding risk when the internal architect can serve both projects. Reviewing the schedules again for float repeats work that is done and pushes architecture work later than either project needs.

Question 9 of 17

A vendor on a hybrid project is under a fixed-price contract with no economic price adjustment clause. The vendor's account manager now asks for an 18 percent increase, citing a rise in component costs, and hints that delivery could slow without it. What should the project manager do FIRST?

  1. A.Reply that the fixed-price contract binds the vendor to the agreed price and ask the account manager to confirm the delivery dates in writing
  2. B.Submit a change request for the increase so the vendor keeps delivering at the current pace while the cost impact is reviewed later
  3. C.Ask the vendor for evidence of the cost change and review it with the procurement manager against the contract terms before responding to the request
  4. D.Meet the account manager with the technical leads and agree on a smaller scope for the next release that offsets the requested increase
Show answer and explanation

Correct answer: C

Contract changes are governed by the agreement and handled with procurement, who holds the authority to modify it, so the first step is to obtain the vendor's cost evidence and review it with the procurement manager against the contract terms. Simply restating that the price is fixed is a positional stance that may be legally correct but can push a struggling vendor toward default and does not test whether the claim has merit. Raising a change request for the full increase concedes before anyone knows whether it is justified. Agreeing on a scope cut with the account manager and technical leads bypasses procurement and trades away value without authority.

Question 10 of 17

On an agile project with a fixed release date and budget, the sponsor asks for a new reporting module to be added to the release. The team's velocity has been stable for six sprints and the release backlog already fills the remaining capacity. What is the BEST way for the project manager to respond?

  1. A.Ask the team to commit to a higher velocity for the remaining sprints and add the reporting module to the release backlog
  2. B.Show the sponsor the release burnup and ask the product owner which lower-value items the module would replace
  3. C.Propose to the sponsor adding the reporting module to the bottom of the backlog for delivery if capacity allows
  4. D.Escalate the request to the steering committee and ask it to approve either more budget or a later release date
Show answer and explanation

Correct answer: B

With time and cost fixed, scope is the variable that can flex, and stable velocity gives objective data to show what fits. Showing the burnup and having the product owner propose which lower-value items the module would displace turns the request into a value trade-off that the sponsor can accept. Asking the team to raise velocity creates unsustainable pressure and an unreliable forecast. Proposing to place the module at the bottom of the backlog avoids the real trade-off and sets up a broken expectation, and escalating to the steering committee is premature when a trade-off within the product owner's authority is available.

Question 11 of 17

A functional manager will release two analysts to your predictive project only if their department gets priority on another initiative. In a follow-up conversation, the manager explains the real concern: without the analysts, the department cannot finish its quarter-end close in six weeks. The project's analysis work over those six weeks is mainly requirements reviews that need about half of the analysts' time. What should the project manager do NEXT?

  1. A.Propose to the functional manager that the department's initiative move up the list at the next portfolio review meeting
  2. B.Ask the sponsor to direct the functional manager to release both analysts on the dates already shown in the resource plan
  3. C.Meet with the functional manager and the other initiative's project manager to agree on a swap of priority between the two competing efforts
  4. D.Propose half-time work for the analysts until the close is done and full-time afterward, and update the resource calendar once agreed
Show answer and explanation

Correct answer: D

Once the underlying interest is known, the project manager can offer an option within their own authority that meets it, and a phased release around the quarter-end close does that. Since the project's work needs only half of the analysts' time until the close, the phased release costs the project little, and the calendar changes once the manager agrees. Offering to move the department's initiative up at the portfolio review trades something the project manager does not control and will damage trust if it does not happen. Asking the sponsor to force the release ignores a legitimate operational need and harms the working relationship. Negotiating a priority swap with the other initiative's project manager is collaborative but still trades portfolio priority, which neither of them owns, and does not address the quarter-end close.

Question 12 of 17

On a hybrid project, a customer insists that a custom export feature be included in the next release. The team rated it low value during refinement, but the customer has never explained what the export is for. What should the project manager do FIRST?

  1. A.Ask the customer to walk the team through the business problem the export is meant to solve
  2. B.Have the team evaluate the feature's cost and send the customer a value score supporting its deferral
  3. C.Ask the product owner to remove the feature from the release since the team rated it as low value
  4. D.Add the export to the release plan as requested and note the team's concerns in the issue log
Show answer and explanation

Correct answer: A

The disagreement rests on an unstated need, so the first step is to understand the problem the customer is trying to solve; the team's low rating may be wrong, or a simpler option may meet the need. Sending a cost-based value score is analysis done only from the team's side and frames the conversation as a case against the customer. Asking the product owner to drop the feature acts on the team's view alone without hearing the customer. Adding the feature as requested concedes without understanding it and may spend capacity on something that does not deliver the intended outcome.

Question 13 of 17

Operations refuses an agile team's deployment window during the retail peak season. The operations lead explains that any outage would hit order processing, and that the freeze policy allows exceptions for low-risk changes with a tested rollback. Which response is MOST likely to produce a durable agreement?

  1. A.Ask the sponsor to request an override of the freeze from the operations director given the business value of the increment
  2. B.Propose to operations holding the completed increments until the peak is over and releasing them together the following month
  3. C.Prepare the release behind feature toggles with a tested rollback plan and submit it through the freeze exception process
  4. D.Hold a joint retrospective with operations to review how the change freeze slows the team's delivery cadence and release flow
Show answer and explanation

Correct answer: C

The operations lead has stated the real interest, protecting order processing, and the policy already offers a path for low-risk changes. Preparing a toggled release with a tested rollback and using the exception process meets that interest while delivering value. Seeking an override through the sponsor uses positional power and ignores a legitimate risk. Proposing to hold the increments until after peak gives up value and creates a large, riskier combined release. A joint retrospective about the freeze is collaborative but targets the policy itself rather than this release and does nothing to resolve the window.

Question 14 of 17

A supplier on a predictive project has missed two milestones and says the delays come from your changing requirements. Your records show three approved change requests during the period. What should the project manager do FIRST?

  1. A.Issue a formal notice of nonperformance to the supplier citing the two missed contract milestones
  2. B.Grant the supplier a schedule extension covering both missed milestones to settle the dispute
  3. C.Ask the business analyst to assess which changes caused the delays and send those findings to the supplier
  4. D.Review the approved change log and milestone records with the supplier to separate the causes of each slip
Show answer and explanation

Correct answer: D

The facts are disputed and partly on the project's side, since three changes were approved, so a durable outcome starts with jointly reviewing the change log and milestone records to separate change-driven delay from the supplier's own slippage. A formal nonperformance notice is premature before the causes are known and may be unfounded for part of the delay. Granting a full extension concedes without evidence and rewards any slippage that was the supplier's own. Having the business analyst assess the delays alone produces a one-sided view the supplier is unlikely to accept.

Question 15 of 17

On a hybrid project, the product owner wants to release on a marketing launch date, but the compliance lead says nothing can go live until the audit trail control is validated, which will take three more weeks. About half the release does not touch regulated data. What is the BEST approach?

  1. A.Propose releasing the features without regulated data on the launch date and the audit-trail features after validation
  2. B.Ask the product owner to make the release decision, since release timing is a product owner responsibility on the project
  3. C.Ask the compliance lead to sign a waiver for the audit trail control with the risk recorded in the risk register
  4. D.Delay the whole release until the audit trail control is validated and move the marketing launch date to match it
Show answer and explanation

Correct answer: A

The compliance requirement is a constraint, not a preference to be traded, while the product owner's real interest is having something to launch on the marketing date. Splitting the release so unregulated features ship on time and audit-trail-dependent features follow validation meets both interests. Leaving the decision to the product owner ignores that compliance obligations sit outside the product owner's authority. Pressing the compliance lead for a waiver pushes them to accept a regulatory risk they are there to prevent. Delaying the whole release is compliant but gives up the launch date for the half of the release that does not need validation.

Question 16 of 17

On an agile project, the finance director wants a weekly cost spreadsheet and the operations VP wants a feature-progress slide, both prepared by the same team. The team now spends half a day each week on reports. What should the project manager do FIRST?

  1. A.Have the team keep producing both formats each week and track the reporting effort as a team impediment
  2. B.Meet each stakeholder to learn which decisions the report supports, then propose one shared dashboard
  3. C.Adopt the operations VP's format for the whole project as the more senior of the two stakeholders
  4. D.Run a workshop with the team to design a combined report format and present it at the next sprint review
Show answer and explanation

Correct answer: B

Each stakeholder's real interest is the decision their report supports, not the layout itself, so learning those needs first makes it possible to propose one shared view that answers both. Continuing to produce both formats concedes to both positions and keeps wasting team capacity. Picking the more senior stakeholder's format uses rank instead of needs and leaves the finance director unsupported. Designing a combined format with the team is collaborative but excludes the people who will use it, so it may meet neither stakeholder's need.

Question 17 of 17

A shared-services team says your predictive project is not important enough for expedited support. Its manager explains that requests are ranked by the portfolio priority list, where your project sits mid-tier, and the standard lead time would delay the critical path by three weeks with no float. Which action is BEST?

  1. A.Ask a contact on the shared-services team to handle the request informally ahead of the standard queue this time
  2. B.Accept the standard lead time and absorb the three-week delay in the schedule baseline at the next update
  3. C.Give the sponsor the quantified delay impact and ask them to raise the priority through portfolio governance
  4. D.Have the team evaluate the schedule again for float and report the options to the shared-services manager
Show answer and explanation

Correct answer: C

The shared-services team is following the agreed portfolio ranking, so changing the order is outside the project manager's authority and belongs in portfolio governance, where the sponsor can present the quantified critical-path impact. Asking a contact to bypass the queue undermines the process and the relationship with the shared-services manager. Absorbing the delay by rebaselining hides a three-week slip that the sponsor should decide on. Re-evaluating the schedule for float repeats an analysis that already found none.

Ready for exam conditions?

Practice these questions with randomized answer order and instant scoring, or take a full domain-weighted mock exam with a real exam timer.