Question 1 of 6
A team member consistently delivers technically excellent work but misses agreed deadlines, impacting downstream tasks. You have mentioned this verbally twice without lasting improvement. What is the MOST appropriate next step?
- A.Document the performance issue formally, set specific measurable expectations with a timeline, and schedule follow-up check-ins.
- B.Reassign the team member to a role with flexible deadlines that better fits their work style — forcing someone into a deadline-driven role they consistently cannot meet creates ongoing performance risk.
- C.Accept the pattern as long as the work quality remains high — tardiness on deadlines is a minor issue compared to the value of their technical contributions to the team.
- D.Immediately escalate to HR for a formal disciplinary process — consistent missed deadlines are a performance issue that falls within HR's mandate to manage.
Show answer and explanation
Correct answer: A
When verbal feedback has not produced lasting improvement, the next step is formal documentation with clear, measurable expectations and follow-up. This is fair, transparent, and gives the team member a clear path to improvement. Reassignment avoids the issue and may not be feasible. Accepting the pattern harms the team and project. Immediate escalation to HR skips intermediate steps and is disproportionate.